Back to the mapIndia Infra Map

Product log

Releases

A short, honest record of what the product can do, what data it contains, and what remains incomplete.

Release 128 reliability correction

Project Briefs now recover automatically from a transient detail-shard read

A published airport could occasionally open the truthful unavailable state even though its reviewed detail record and evidence shard were healthy. Selected-record delivery now retries the static shard read at the edge and retries the brief or specialist request in the interface before showing an error.

Preserved: the airport record, source evidence, cost and schedule meanings, map position, spatial precision, discovery state, selected-marker framing, and explicit failure fallback are unchanged. A genuine repeated failure still produces the existing retryable unavailable state instead of inventing a brief.

Releases 124–127 discovery checkpoints

Filters and shared-location cycling deepen discovery without changing project facts

The optional BEE layer adds operator and connector filters. Core discovery adds progress, compatible cost and deadline movement, exact-role families, and stable marker cycling when reviewed records share one source point.

Limit: missing or incomparable values remain separate. Role families are search aids; Project Briefs and Evidence retain exact source wording, without implying ownership, operation, blame, or misconduct.

Release 123 data release

Four hundred and eight cold-chain project entries expand logistics coverage without turning districts into facility sites

The catalog contains 11,027 source-backed records: 10,938 core non-toll records and 89 optional toll-plaza facilities. The separate optional EV charging lane remains 27,922 accepted facilities and contributes zero to the core inventory count.

Complete bounded inventory

All 408 rows in the Ministry's 31 March 2026 approved cold-chain inventory become auditable baseline project entries: 309 reported Completed and 99 reported Ongoing at that evidence cutoff.

Representative navigation only

District, locality, or broad State/UT anchors come from a separately attributed gazetteer. They are not project sites, facility footprints, service areas, or construction geometry.

Lifecycle stays evidence-dated

Completed does not prove commissioning, inauguration, current operation, or 100% progress. Ongoing does not by itself prove physical construction, delay, or present activity after the cutoff.

Source conflicts stay visible

Twenty-four released-grant cells remain missing. The row-level revised-grant sum conflicts with the printed grand total, and two rows contain impossible money ordering; no value is corrected or used for derived comparisons.

Identity and role limit: four normalized names repeat in separately numbered approval rows with different approval dates. They remain distinct source-established entries without inferred phase or parent relationships. The source does not establish owner, operator, contractor, concessionaire, or EPC roles.

Local validation: source, money, spatial, containment, read-model, and D1 validators passed with clean idempotent replay and static parity. The 498-test suite, lint, minified production build, healthy and failed-basemap review, and responsive checks at 320, 390, 820, 1180, 1440, and 1920 pixels passed without horizontal overflow or browser errors.

Release integrity: the validated source, generated discovery artifacts, and ordered D1 migrations are versioned together. Production D1 is activated only after clean replay, semantic parity, and public-route verification.

Release 122 local data candidate

Forty-one Mega Food Park projects add a complete Ministry inventory without flattening status, grants, or geography

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,619 source-backed records: 10,530 core non-toll records and 89 optional toll-plaza facilities. Public production remains Release 97 with 10,204 records.

Complete bounded table review

All 41 rows in the Ministry's 31 August 2025 Mega Food Parks table become auditable baseline industrial-park projects. No candidate is hidden, duplicated, rejected, deferred, or left pending.

Representative locality navigation

Every point comes from a separately attributed locality record. It is not a surveyed food-park site, parcel, gate, processing centre, or project boundary.

Status remains evidence-dated

Operational, Operational and Complete, and Under Implementation remain observations at the table cutoff. Combined wording becomes separate dated events, not proof of present lifecycle.

Money remains typed

Project cost, approved grant, and released grant remain separate. The printed approved-grant total exceeds the row sum by ₹6.45 crore, so the source difference stays explicit.

Role and evidence limit: each published SPV is labelled Source-listed SPV / implementing agency. It is not relabelled as owner, operator, contractor, concessionaire, or EPC provider, and procurement, payments, current lifecycle, and exact geometry remain missing unless separately sourced.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 121 local data candidate

Eighteen evidence-dated non-major-port projects expand the inventory without forcing unresolved geography

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,578 source-backed records: 10,489 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Complete bounded table review

All 21 rows in the Ministry's ongoing non-major-port project appendix are auditable. Eighteen become baseline records, one Honnavar row links to the same canonical project, and two remain held.

Unresolved points stay off the map

Redi and Subarnarekha remain needs-review candidates because the reviewed navigation evidence did not establish unambiguous project anchors. A river point or unrelated locality is not substituted.

Status remains dated

Operational, construction, clearance, agreement and progress wording is bounded to 30 September 2025. It is not presented as proof of present lifecycle or condition.

Money semantics stay exact

Project-cost entries are not relabeled as sanctioned cost, award, expenditure, payment or final cost. Karanja's printed 0.0 remains an unresolved raw value rather than a supported zero-cost claim.

Spatial and entity limit: all accepted markers are representative. Honnavar's two rows remain linked with their conflicting 4.9 versus 5 MTPA and ₹613 crore versus ₹607.03 crore observations visible in the ledger.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 120 local data candidate

The current official NIXI directory resolves all 79 facilities while preserving historic lifecycle boundaries

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,560 source-backed records: 10,471 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Full current directory reconciled

All 79 rows in NIXI's public NOC directory are auditable. Forty-two link to stable Release 119 identities and thirty-seven become new baseline facilities.

Bad embedded maps excluded

Official addresses remain evidence, but wrong-city, displaced, and missing embedded maps do not become project coordinates. Every marker stays at representative locality precision.

Listing is not operation

Directory presence and the API publication flag do not establish operation, commissioning, capacity, traffic, uptime, ownership, or service quality.

Historic events remain dated

Only the 42 linked facilities retain the separate reported-operational event dated 9 December 2022. The thirty-seven new rows receive no inferred operational lifecycle.

Privacy and evidence limit: source-published addresses are retained, while contact names, phone numbers, and email addresses remain only in the frozen audit source and are omitted from product records. Exact exchange racks, buildings, routes, contracts, costs, and current performance remain missing.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 119 local data candidate

Forty-two historic NIXI Internet Exchange facilities expand Digital & Telecom without inventing the current location gap

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,523 source-backed records: 10,434 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Complete historic annexure

All 42 locations named in Rajya Sabha Unstarred Question 404 become auditable baseline facility records with stable source-row identities.

Representative locality navigation

Markers orient users to the named city or locality. They are not exchange sites, data-centre addresses, racks, network routes, service boundaries, or surveyed geometry.

Lifecycle remains evidence-dated

The official answer reported the 42 exchanges installed and operational on 9 December 2022. The product does not carry that state forward as confirmed current operation.

Current aggregate gap stays visible

A newer official statement reports 79 IXPs nationwide but supplies no row-level locations. The other 37 are recorded as a coverage gap and are not fabricated.

Spatial limit: Chennai 1 and Chennai 2 remain separate source records at the same representative Chennai anchor. Chandivali uses broader Mumbai orientation because no unambiguous reviewed locality point was available. No coordinate is jittered or upgraded to facility-site precision.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 118 local evidence candidate

Seventy deferred CEA rows are now auditable without creating State-centroid projects

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog remains 10,481 source-backed records: 10,392 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Deferred rows 156 through 225 reviewed

All seventy rows now have auditable dispositions. None is accepted, duplicated, or rejected; all remain needs-review candidates rather than disappearing from the source ledger.

No invented geography

Every row publishes only State-level geography. No State centroid, silent locality, project point, route, parcel, or geometry is created.

Repeated identities stay unresolved

Generic procurer labels, blank project-label cells, and repeated developer-State-type combinations remain held until project-specific authoritative evidence establishes identity and relationships.

Catalog totals remain honest

Zero rows enter map markers, results, Project Briefs, Energy Generation totals, or the 10,000-project count. The 18,587.3 MW partition total remains a source checksum only.

Evidence limit: needs-review is not rejection and does not prove that the underlying projects are invalid, inactive, or absent. A later authoritative project source may resolve identity and geography.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 117 local data candidate

Twelve locality-backed CEA renewable projects extend the inventory while sixteen uncertain rows remain held

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,481 source-backed records: 10,392 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded rows 226 through 253

The seventh reviewed partition contains 28 candidates. Twelve become canonical projects and sixteen remain auditable needs-review rows. Rows 156 through 225 are explicitly deferred rather than counted as reviewed.

Representative navigation only

Accepted map points are separately attributed locality or city orientation. Shared Lakadia, Bikaner, and other anchors remain source-locked and never become project sites or geometry.

Ambiguous rows stay off the map

Repeated generic schemes, unresolved project-component relationships, and localities without defensible navigation remain held instead of becoming invented separate projects or State-centroid markers.

Source differences remain visible

Tawargere versus Tavaragera and Davangere versus Davanagere stay explicit. Blank and qualified schedule fields remain missing or conflicting rather than becoming no-change claims.

Evidence limit: the CEA table publishes no project coordinates or geometry. It reports developers, places, capacities, and schedule columns but does not establish current output, physical progress, cost, expenditure, contractor roles, or post-cutoff operation.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 116 local data candidate

Ten locality-backed CEA renewable projects extend the inventory while one blank-name State-only row remains held

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,469 source-backed records: 10,380 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded rows 145 through 155

The sixth partition of the frozen March 2026 CEA report contains eleven candidates. Ten become new projects and the blank-name Rajasthan-only row remains auditable needs-review evidence.

Representative navigation only

Ralla, Pattikonda, Aski, and Khambhaliya use reviewed locality orientation. Unresolved villages use directly labelled administrative orientation without becoming project sites or geometry.

Geographic differences stay visible

The reviewed Nokh result uses Jaisalmer context while CEA publishes Phalodi district. The record therefore uses broader Phalodi orientation and preserves the difference.

Compound dates remain literal

Multi-date, qualified, and NA schedule fields remain raw evidence unless both source columns contain one valid compatible date.

Evidence limit: the CEA table publishes no project coordinates or geometry. It reports developers, places, capacities, and schedule columns but does not establish current output, physical progress, cost, expenditure, contractor roles, or post-cutoff operation.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 115 local data candidate

Eighteen more CEA renewable projects extend the inventory while twenty-two ambiguous rows remain held

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,459 source-backed records: 10,370 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded rows 105 through 144

The fifth partition of the frozen March 2026 CEA report contains 40 candidates. Eighteen become new projects and twenty-two remain auditable needs-review rows.

Representative navigation only

Every accepted point is separately attributed orientation. Exact lookup gaps, broader administrative fallbacks, and shared anchors stay explicit and never become project sites or geometry.

Repeated identities stay unresolved

State-only rows, repeated holding-company labels, possible revisions or components, and the unresolved Hunsagi/Bijapur placement remain off the map rather than being forced into canonical records.

Schedule evidence stays typed

Purvah Bijapur One supports a 396-day scheduled-to-anticipated movement. Source rows carrying NA remain missing instead of becoming no-change or conflict claims.

Evidence limit: the CEA table publishes no project coordinates or geometry. It reports developers, places, capacities, and schedule columns but does not establish current output, physical progress, cost, expenditure, contractor roles, or post-cutoff operation.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 114 local data candidate

Fifteen more CEA renewable projects extend the inventory while eight uncertain source rows remain held

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,441 source-backed records: 10,352 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded rows 82 through 104

The fourth partition of the frozen March 2026 CEA report contains 23 candidates. Fifteen become new projects and eight remain auditable needs-review rows.

Representative navigation only

Every accepted point is separately attributed orientation. Reused locality and administrative anchors remain unchanged and never become project sites or geometry.

Source identity stays literal

Non-finalized project names, one multi-state row, and an unclear portfolio-level identity stay off the map instead of being resolved through inference.

Tentative dates stay qualified

The Diyos row supports a 41-day scheduled-to-anticipated movement, while the source's tentative qualifier remains visible and does not become a guaranteed deadline.

Held evidence: two rows have zero commissioned and zero under-construction capacity, four publish Not Finalized as the project name, one combines Rajasthan solar and Karnataka wind without defensible point geometry, and one uses an organization name as both project and developer without a stable project identity.

Spatial limit: the Balai Kesharpura lookup returned no feature, so the Tejorupa record uses a broader Sheo locality point with the conflict stated directly. No accepted marker is CEA project geometry.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 113 local data candidate

Twelve more CEA renewable projects extend the reviewed inventory while conflicting and unconfirmed rows stay off the map

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,426 source-backed records: 10,337 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded rows 62 through 81

The third partition of the frozen March 2026 CEA report contains 20 candidates. Twelve become new projects, three link to existing NGEL records, and five remain held.

Representative navigation only

Every accepted point is separately attributed orientation. Reused solar-park and administrative anchors remain unchanged and never become project sites or geometry.

Capacity and schedule stay literal

Execution, commissioned, and under-construction capacity remain separate source columns. Inverted date pairs remain conflicts instead of becoming delay claims.

Partial commissioning stays scoped

The IRCON Pavagada row preserves 400 MW commissioned and 100 MW under construction as of March 2026 without claiming current output, complete operation, or full project completion.

Held evidence: one 640 MW row has an internally inconsistent zero commissioned and zero under-construction split; one Serentica row conflicts between Bhadla and Bikampur; and three Tilaiya or Panchet rows do not explicitly establish their apparent relationship to the existing DVC Floating Solar Park Phase I.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 112 local data candidate

Twelve more CEA renewable projects extend the reviewed execution inventory while nineteen uncertain or duplicate rows stay out of the count

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,414 source-backed records: 10,325 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded rows 31 through 61

The same frozen March 2026 CEA report contributes 31 NHPC, SJVN, and first DVC candidates. Twelve become new projects, five link to existing solar-park systems, and fourteen remain held.

Representative navigation only

CEA publishes no project coordinates in the table. Separately attributed place and landmark points remain orientation, while shared Khavda and administrative anchors stay source-locked without jitter.

Capacity and schedule stay source-scoped

Execution, commissioned, and under-construction capacity remain separate. Scheduled and anticipated dates retain their exact meanings and are never converted into present progress or operation.

Uncertainty remains auditable

Repeated identities, multi-state or distributed geography, State-only placement, and an invalid source-type value remain in the candidate ledger rather than becoming misleading markers.

Source differences: Mirzapur and Odisha capacity observations differ from earlier canonical solar-park records, so they remain linked evidence conflicts rather than overwriting the existing values. Bagodara preserves the source difference between its name and the Surendranagar location column.

Local validation: source and spatial validators, clean idempotent D1 replay, D1/static parity, the complete automated suite, lint, the minified production build, responsive rendered review at 320, 390, 820, and 1440 pixels, selected-record state restoration, and deliberate basemap-failure isolation passed. No fresh 1180- or 1920-pixel browser capture was produced for this data-only checkpoint.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 111 local data candidate

Twenty-seven CEA renewable projects add source-scoped capacity and schedule evidence without duplicating two solar-park systems

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,402 source-backed records: 10,313 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Bounded 30-row partition

The complete 78-page CEA report is frozen, while this checkpoint reviews only numbered NTPC rows 1 through 30. Twenty-seven become new projects, two link to existing systems, and one State-only row remains held.

Representative navigation only

Every new point is separately attributed orientation. Shared Khavda, Kalasar, Bikaner, Chitrakoot, and multi-site anchors remain source-locked without jitter and never become project geometry.

Capacity columns stay distinct

Capacity for execution, commissioned capacity, and under-construction capacity are not converted into physical progress, output, storage, expenditure, or complete operation.

Schedule conflicts remain visible

Scheduled and anticipated completion are compared only for valid, chronologically compatible dates. The invalid Gadag date and inverted Fatehgarh-I pair remain explicit source conflicts.

Evidence limit: CEA does not publish project coordinates or geometry in this table. The source role remains Source-listed developer, and a March 2026 status is not carried forward as current without newer evidence.

BESS source gap: the reviewed April 2026 CEA battery-storage report contains national aggregates but no project identities. The linked May 2026 PDF returned 404 during review, so neither source produced inventory records.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 110 local data candidate

Fifty-two CEA solar-park systems expand the energy inventory while three ambiguous locations remain held

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The Release 110 candidate contained 10,375 source-backed records: 10,286 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remained outside the core inventory. Public production remained Release 97 with 10,204 records.

Complete 55-row source universe

The March 2026 CEA Solar Parks / UMREPPs report contributes 52 new baseline systems across thirteen States. Patoda, Bodana, and UP Solar Park remain needs-review because the table does not support an unambiguous map placement.

Shared anchors, no invented sites

Khavda, Pugal, Bhadla, and Kasaragod phases retain shared reviewed locality anchors without jitter. Multi-site and administrative points are labelled as orientation, never as park boundaries, parcels, generation units, or surveyed geometry.

Mixed completion field stays source-scoped

CEA's Actual/Anticipated Solar Park Completion Date column is not converted into present operation or full nested-project completion. Completed, anticipated, under-development, and no-activity wording remain distinct.

Capacity and agency roles stay exact

Total park capacity is not treated as commissioned generation, output, or storage. Every organization keeps the exact role Source-listed solar park agency, not contractor, owner, operator, or concessionaire.

Evidence limit: the table can describe several nested plants, land parcels, transmission components, tenders, and commissioning events in one row. Those narratives remain attributable evidence and are not collapsed into one synthetic progress, cost, schedule, or lifecycle verdict.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 109 local data candidate

Twenty-one CEA hydro projects extend the execution inventory without duplicating nineteen existing records

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,323 source-backed records: 10,234 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Complete 40-row workbook

The June 2026 CEA workbook contributes 29 conventional hydroelectric and 11 pumped-storage rows. Twenty-one become new canonical projects and 19 link to existing records rather than inflating the catalog.

Representative navigation only

Every new point is separately attributed locality navigation. None is a CEA project coordinate, dam, powerhouse, reservoir, tunnel, surveyed worksite, or full project geometry; shared locality anchors remain source-locked.

Execution remains source-dated

Under implementation is preserved as of 30 June 2026. It does not establish present construction activity, completion, commissioning, opening, operation, delay, or performance after that cutoff.

Targets and roles stay exact

The source's finish or commissioning field is a current reported target, not a derived deadline revision. Each named organization retains only the exact role Executing agency.

Evidence limit: the workbook does not publish reusable project coordinates or complete geometry. It also does not by itself establish original deadlines, revised deadlines, present progress, project cost, award, expenditure, payment, actual cost, final cost, or current operation.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 108 local data candidate

Fifteen operational land ports add a bounded cross-border logistics facility lane

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,302 source-backed records: 10,213 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Complete 15-facility roster

The June 2026 Ministry releases and current LPAI roster reconcile to fifteen accepted canonical land ports with no duplicate, held, rejected, or unnamed planned facility added.

Representative navigation only

Every point is separately attributed town, village, or locality context. None is a land-port gate, terminal, customs building, parcel, boundary, surveyed site, or complete facility geometry.

Operation remains source-dated

The Ministry reported LPAI operating the roster on 7 June 2026. That does not establish an opening date, completion, commissioning, inauguration, uninterrupted later operation, traffic, capacity, or performance.

Exact source role retained

Land Ports Authority of India is labelled only as the land-port operating and managing authority. No contractor, concessionaire, customs operator, project award, or ownership role is inferred.

Source difference: the newer Ministry operational statement governs Sabroom's dated current read, while an older LPAI detail page retaining September 2021 pre-construction wording remains visible as a source difference rather than being erased.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 107 local data candidate

Seven reviewed Gandhinagar mine assets extend inspection evidence without turning locality landmarks into mine sites

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,287 source-backed records: 10,198 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

One auditable 120-row source universe

Three current IBM Gandhinagar register pages provide 120 candidate rows and 25 linked mine-specific reports. Seven unique mine codes publish, two earlier same-code revisions remain linked, and 111 candidates remain held.

Locality and landmark points stay representative

Four accepted points use separate locality records. Three use public locality landmarks whose reviewed address establishes the source village, district, and state. None is an IBM mine coordinate, lease centroid, extraction footprint, boundary, or surveyed geometry.

Inspection remains an evidence event

A dated MCDR inspection does not establish present operation, production, compliance, completion, commissioning, suspension, or closure. Missing current lifecycle evidence stays explicit.

Official names remain intact

Source-published Devanagari mine names are preserved without encoding damage. Deterministic English village, mineral, and mine-code aliases improve search without replacing official identity.

Privacy and source boundary: contact and inspection-administration fields in the public reports are excluded. Five register/report date conflicts, invalid or missing stable codes, unavailable reports, and unresolved geography remain held.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 106 local data candidate

Twenty-four reviewed mine assets add current IBM inspection evidence without inventing operation or mine-site precision

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,280 source-backed records: 10,191 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

One auditable 180-row source universe

Five current IBM regional registers provide 180 candidate rows and 170 linked mine-specific reports. Twenty-four unique mine codes publish, eight duplicate or revision rows remain linked, and 148 candidates remain held.

Representative localities, never mine sites

Every accepted point independently matches the report's locality, district, and state. It remains a locality-navigation point, not an IBM coordinate, lease centroid, extraction footprint, boundary, or surveyed geometry.

Inspection is not operation

A dated MCDR inspection establishes the recorded event only. Present operation, production, compliance, completion, commissioning, and suspension remain unknown unless a separate attributable source establishes them.

Regulatory attention stays non-accusatory

A listed violation or show-cause letter is labelled with its date and source limitation. It is not presented as an adjudication or evidence of misconduct, corruption, blame, or project failure.

Privacy and source boundary: the public reports contain contact and inspection-administration fields. The product extracts only non-sensitive project identity, exact source role, dated inspection, mineral, administrative place, and reviewed mine attributes needed for infrastructure discovery.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 105 local data candidate

Seven reviewed public space-launch records activate a dedicated infrastructure category

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,256 source-backed records: 10,167 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Seven distinct infrastructure records

One spaceport, three public launch pads, one sounding-rocket facility, one new launch-complex project, and one private launch facility retain distinct identities. Nine candidates remain auditable: seven accepted and two held.

Exact and representative geography stay separate

Three official facility coordinates remain exact source points. Four other records use clearly labelled representative anchors without becoming pad, range, parcel, boundary, worksite, or security geometry.

Lifecycle meanings stay separate

Active, operational, inaugurated, approved, and under construction remain source-dated meanings. An inauguration or first launch does not establish completion, commissioning scope, continuous operation, or present readiness.

One reviewed category activation

The existing solid launch pictogram becomes the eighteenth maintained category only after the bounded source, safety, identity, relationship, taxonomy, and rendering review.

Relationship and source boundary: four source-backed child relationships connect the First, Second, and Third Launch Pads and Agnikul Launchpad-01 to SDSC SHAR. Shared Sriharikota anchors are preserved without coordinate jitter or record merging.

Held candidates: Skyroot's Infinity Campus and Max-Q Campus remain needs review because the official sources reviewed here do not yet reconcile their names, sites, and relationship strongly enough for canonical publication.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 104 local data candidate

Seven reviewed shipbuilding and ship-repair records activate a dedicated infrastructure category

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,249 source-backed records: 10,160 core non-toll records and 89 optional toll-plaza facilities. The separate 27,922-facility EV lane remains unchanged and does not count toward the core inventory. Public production remains Release 97 with 10,204 records.

Seven distinct infrastructure records

Two development projects, two shipyard assets, and three ship-repair units retain distinct identities and source-published roles. Nine candidates remain auditable: seven accepted and two held for missing publishable site evidence.

Representative geography only

Official facility addresses are paired with separately attributed navigation points. Every marker remains representative and does not become a dry dock, berth, yard boundary, parcel, production area, or surveyed project geometry.

Lifecycle meanings stay separate

Two 17 January 2024 inauguration events remain separate from later reported-operation evidence. Dedication, construction completion, commissioning, opening, and present operation are never inferred from one another.

One reviewed category activation

The existing solid shipbuilding pictogram becomes the seventeenth maintained category only after the bounded source, overlap, taxonomy, and rendering review. Space launch remains a visual-only prototype.

Money and source boundary: ₹1,799 crore, ₹970 crore, ₹168 crore, ₹180 crore, ₹175.20 crore, and ₹70 crore observations retain their published dates and definitions. No compatible cost-revision sequence is inferred.

Held proposals: the official 2025 Kochi block-fabrication and Tamil Nadu greenfield-shipyard proposals remain needs review because the sources do not establish a publishable approved site and source-backed map position. The reported Tata Kerala facility remains outside the ledger because no authoritative reusable source was located.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 103 local interface candidate

EV charging discovery moves from a full browser catalog to bounded D1-first reads

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The core app catalog remains 10,242 records and the 27,922 accepted EV facilities contribute zero to the core 10,000-project count. Public production remains Release 97 with 10,204 records.

D1-first, static-safe read contract

A versioned API queries accepted EV candidates by search, State/UT, district, viewport, zoom, cursor, or exact record. If the compatible D1 binding or query is unavailable, the server reports a classified static fallback instead of weakening discovery.

Bounded source-locked activation

The client receives one 24-row result page and only the zoom-aware features needed for the current map state: 700 nationally, 1,800 regionally, or up to 8,000 inside a close viewport. Coordinates remain unchanged and no clustering or jitter is introduced.

Exact semantic parity

Clean local migration replay proves 27,922 accepted and 1,444 held facilities. Six representative D1/static states, cursor traversal, direct selection, accepted-only counts, and held-record exclusion match exactly.

Smaller first EV response

The measured local static-fallback opt-in response is roughly 221 KB for 24 rows plus 700 national points, compared with the earlier 1.91 MB browser catalog. A named two-result search is roughly 19 KB.

Scale boundary: a dense Maharashtra close-view response measured roughly 507 KB for 1,850 active points. The server fallback also parses and caches the full static source on its first request. Production D1 latency and cache behavior remain unverified until the original owning account returns.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered migration audit, clean replay, complete release gate, and production verification from the original account.

Release 102 local interface candidate

Reviewed EV charging facilities become an explicit, progressively loaded discovery layer

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The core app catalog remains 10,242 records and the 27,922 accepted EV facilities contribute zero to the core 10,000-project count. Public production remains Release 97 with 10,204 records.

No EV payload on a fresh map

The default non-toll view remains 10,153 records and requests no EV charging data. Explicit layer activation, deliberate EV search, or a direct facility URL loads one versioned 1,907,209-byte compressed spatial index.

27,922 individual optional features

Every accepted BEE facility remains source-locked in native MapLibre layers without clustering, jitter, coordinate substitution, or DOM markers. The complete active count stays visible even when progressive draw priority limits national-screen density.

Evidence-dated facility brief

The brief exposes BEE's CPO field, connector rows, evidence cutoff, CRS, official-facility precision, source, and gaps. A dated listing is not presented as present operation, availability, ownership, commissioning, price, access, or connector serviceability.

Composable and reversible discovery

The layer composes with search, filters, lenses, result paging, selected facilities, Back, Home reset, and shareable `ev=1` URLs. A named hidden match offers an explicit route to enable the layer instead of silently returning nothing.

Scale boundary: the compressed static index is an independently healthy local fallback and proves the interaction contract. Production-scale viewport queries and cursor pagination should move to D1 after the original owning account returns and exact parity is revalidated.

Account boundary: no Sites version, deployment, remote D1 write, hosting change, or remote push occurred. Publication remains queued behind an ordered clean-database replay and complete release gate from the original account.

Release 101 local data candidate

Nationwide BEE public EV charging inventory staged without claiming present operation

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. This checkpoint does not change the active 10,242-record app catalog or the core 10,000-project count. Public production remains Release 97 with 10,204 records.

29,366 auditable facility candidates

The frozen BEE PDF yields 39,641 source rows, 31,213 unique exact rows, and 29,366 deterministic facility identities. BEE publishes no stable station identifier, so these IDs remain local review keys.

27,922 accepted across 36 State/UT scopes

Accepted points pass coordinate, India-bounds, source-state, and independent district-containment gates. Another 1,444 records remain held for malformed text, conflicts, shared coordinates, or ambiguous identities.

Listing is not present operation

Each record means only that the facility appeared in BEE's dataset through 26 October 2025. Availability, access hours, price, ownership, commissioning, and connector serviceability remain unestablished.

Optional-layer staging only

EV charging uses the existing Logistics & Inland Transport category and `ev-charging` presentation subtype. It is queued as an optional facility layer and contributes zero to the core-project inventory count.

D1 boundary: eight local SQL artifacts preserve all accepted and held dispositions in a dedicated candidate table. Clean SQLite replay and a second application retain identical candidate and search counts. No migration has been applied remotely.

Interface boundary: the active spatial index remains 10,242 records and contains no EV charging facilities. Search, map, URL, result, selection, and optional-layer integration remain a later validated checkpoint.

Account boundary: publication remains queued until the original Sites-owning account returns, accumulated migrations replay in order, and the exact candidate passes the full release gate again.

Release 100 local candidate

Sleemanabad and Bargi Diversion Phase III linked without creating a duplicate project

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. This candidate is not saved, deployed, or applied to remote D1. The candidate catalog remains 10,242 source-backed records: 10,153 core non-toll records and 89 optional toll-plaza facilities. Public production remains Release 97 with 10,204 records.

One linked component

The Sleemanabad carrier-canal tunnel is attached to existing Bargi Diversion Phase III because its published RD 104–129 scope sits within Phase III's km 104–154 range. No new marker or canonical project is created.

Unchanged representative geography

The parent's corridor representative point remains unchanged. No tunnel alignment, portal, worksite, parcel, command area, or exact site is invented.

Contracts and audit replies preserved

Two historical contracts, one differently defined running-bill value, and three CAG observations retain their published scopes, dates, department replies, audit responses, and limitations.

Current milestone remains held

July 2026 breakthrough reports were not backed by a located government release or exchange filing, so they remain discovery leads rather than published project evidence.

Money boundary: ₹799 crore turnkey award, ₹9.76 crore grout-block contract, ₹1,356.05 crore running-bill work value, and the ₹13.24 crore, ₹39.60 crore, and ₹6.20 crore audit observations retain different meanings and are not compared as a cost-revision sequence.

Status boundary: the parent's June 2026 snapshot remains 81.52% progress with a December 2026 revised target. Historical excavation, monitoring, extension, and under-execution evidence does not establish tunnel breakthrough, completion, commissioning, water release, or operation.

Account boundary: publication remains queued until the original Sites-owning account returns, accumulated migrations replay in order, and the exact candidate passes the full release gate again.

Release 99 local candidate

Bhogapuram airport development added without collapsing construction, licensing, opening, or cost meanings

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,242 source-backed records: 10,153 core non-toll records and 89 optional toll-plaza facilities. Public production remains Release 97 with 10,204 records.

One distinct development project

Bhogapuram remains separate from the unresolved DGCA airport-asset candidate and the existing NHAI airport-connectivity package. The relationships stay explicit without merging identities.

Official airport reference point

The AAI coordinate supports airport-level navigation. It is not a terminal, boundary, runway endpoint, parcel, construction footprint, or complete project geometry.

Lifecycle meanings stay separate

The latest reviewed source reports 98.74% construction progress on 6 April 2026. Licensing, inauguration, commissioning, opening, and commercial operation remain unestablished.

Three money definitions

The 2016 proposal cost, 2017 approximate construction estimate, and 2023 Phase 1 estimate retain their different scopes. No cost-change value is derived.

Source boundary: four official HTML sources are frozen and fingerprinted. The public AAI coordinate PDF was reviewed, but repeated direct downloads timed out, so the linked coordinate remains attributable without a claimed immutable local PDF hash.

Containment boundary: the official point passes coordinate-order, India-bounds, Andhra Pradesh, Vizianagaram, airport-identity, and source-context review. The frozen Release 97 polygon snapshots remain unchanged, so no newer independent polygon-containment result is claimed.

Account boundary: publication remains queued until the original Sites-owning account returns, accumulated migrations replay in order, and the exact candidate passes the full release gate again.

Release 98 local candidate

Thirty-seven PPPAC Port projects prepared locally with appraisal and revision meanings intact

LOCAL ONLY, NOT SAVED, NOT DEPLOYED, REMOTE D1 UNCHANGED. The candidate catalog contains 10,241 source-backed records: 10,152 core non-toll records and 89 optional toll-plaza facilities. Public production remains Release 97 with 10,204 records.

Complete 43-row source universe

Thirty-seven rows form new canonical project records, five remain linked without double-counting, and one 2009 Ennore row remains needs-review.

Navigation is not project geometry

Source-backed major-port, Diamond Harbour, and Sahibganj points retain official-facility or representative precision. None becomes a port boundary, berth, terminal, route, parcel, or complete project extent.

Two compatible revisions

VOC Outer Harbour and JNPT Fourth Container Terminal expose only the explicitly comparable PPPAC total-project-cost observations. Other list values remain separately typed.

Local D1 artifacts only

Idempotent Release 98 and discovery migrations replay in a clean temporary database and match the versioned static read models. They have not been applied remotely.

Status boundary: PPPAC final or in-principle approval is dated appraisal evidence. It does not establish current procurement, concession, construction, completion, commissioning, opening, operation, or ownership.

Containment boundary: the frozen Release 97 state and district snapshots still cover the 10,204 released records. The 37 local additions pass frozen-source coordinate, State/UT, India-bounds, precision, and limitation checks, but no new independent polygon-containment result is claimed.

Account boundary: publication remains queued until the original Sites-owning account returns, the accumulated local work is audited, migrations are replayed in order, and the exact candidate passes the full release gate again.

Release 97

Ten PPPAC Airport appraisal projects with approval and money meanings intact

The public catalog expands to 10,204 source-backed records: 10,115 core non-toll records and 89 optional toll-plaza facilities. The complete 10-row Airport subset of the official PPPAC project list publishes as distinct projects linked to eight existing DGCA airport assets.

One complete official subset

All ten Airport candidates, three meeting records, dispositions, source fingerprints, and project-to-asset links remain auditable in the D1 control plane.

Airport relation, not invented geometry

Each project reuses the unchanged representative point of its exactly matched airport asset. The point is not a selected-area boundary, city-side parcel, concession extent, terminal, or construction site.

Money types do not collapse

Six rows expose estimated concessionaire investment. Four source-table zeroes remain raw observations while the public project-cost field stays Not published.

Approval is dated evidence

Eight final-approval and two in-principle-approval records retain their 2008, 2016, or 2018 meeting dates and do not claim present implementation or operation.

Role boundary: Airports Authority of India or Ministry of Civil Aviation appears only as PPPAC table sponsoring authority. The lane does not infer an owner, contractor, concessionaire, selected bidder, operator, or implementing agency.

Money boundary: estimated concessionaire investment is not original cost, revised cost, award value, expenditure, payment, actual cost, or final cost. A source-table `0.00` is not presented as zero project cost.

Status boundary: PPPAC appraisal approval does not establish current procurement, agreement execution, construction, operation, completion, inauguration, commissioning, opening, or ownership.

Release 96

Ninety-nine Smart Cities ICCC systems with dated status and locality-level maps

The public catalog expands to 10,194 source-backed records: 10,105 core non-toll records and 89 optional toll-plaza facilities. Digital & Telecom grows from 37 to 136 records through a nationwide Integrated Command and Control Centre baseline lane.

All 100 candidates stay auditable

Ninety-nine city systems publish. New Town Kolkata remains needs-review because the reviewed navigation source does not provide one unambiguous locality feature.

Representative locality navigation

GeoNames supplies WGS 84 city anchors under CC BY 4.0. They are not ICCC buildings, control rooms, service boundaries, municipal polygons, or connected-system geometry.

Evidence-dated operational wording

MoHUA reported ICCCs established across all 100 Smart Cities as of 15 November 2024. The product does not carry that statement forward as confirmed July 2026 operation.

One exact organization role

Ministry of Housing and Urban Affairs appears only as Source reporting ministry. No city SPV, owner, operator, contractor, bidder, or delivery organization is inferred.

Identity boundary: the OGD city list establishes the 100-city Smart Cities Mission universe and selection round under the Government Open Data License - India. It does not establish a control-room site, contractor, cost, deadline, capacity, or current status.

Status boundary: the 2024 nationwide MoHUA statement does not prove uninterrupted service, current integrations, performance, capacity, ownership, commissioning scope, or present operation in any city.

Coverage boundary: city-specific tenders, contracts, amendments, costs, payments, audits, operators, stronger geometry, and newer status evidence remain explicit enrichment gaps.

Release 95

Zojila Tunnel contract trail with its source conflict intact

The public catalog expands to 10,095 source-backed records: 10,006 core non-toll records and 89 optional toll-plaza facilities. The held PAIMANA candidate is now resolved through dedicated NHIDCL and PIB evidence without rewriting its incorrect Andhra Pradesh state field.

Six linked official sources

Current status, tender schedule, award, dated status, breakthrough, and PAIMANA observations retain separate fingerprints, dates, roles, values, and interpretation limits.

Cross-UT corridor representation

The map derives one navigation midpoint from two approximate schedule endpoints across Jammu and Kashmir and Ladakh. It is not a tunnel portal, route alignment, site, or surveyed geometry.

Three different money meanings

₹6,808.69 crore current TPC, ₹4,509.50 crore EPC award value, and ₹3,215.86 crore cumulative expenditure remain separate and are not presented as a cost-revision sequence.

Milestone is not completion

The 9 June 2026 main-tunnel breakthrough is shown as a construction event. It does not establish completion, commissioning, opening to traffic, or operation.

Schedule boundary: the current NHIDCL row moves the likely completion from 30 September 2026 to 28 February 2028, a 516-day change. Its 69% physical and 63% financial figures use the 19 July retrieval date because the row publishes no separate observation date.

Source-difference boundary: PAIMANA's Andhra Pradesh field, the 2024 PIB length/cost/schedule figures, and the rounded 2026 breakthrough values remain visible differences rather than silent corrections.

Evidence boundary: no signed EPC agreement, amendments, certified payment ledger, disputes, audits, actual cost, final cost, completion, commissioning, opening, or operation is inferred.

Release 94

Vadhavan Port as a distinct contract-linked development project

The public catalog expands to 10,094 source-backed records: 10,005 core non-toll records and 89 optional toll-plaza facilities. Vadhavan is now represented as a development project, not an operating port asset or an alias for its separate highway-connectivity packages.

Four fingerprinted official sources

Cabinet approval, JNPA project information, the VPPL package award, and the environmental filing retain separate source roles and immutable fingerprints.

One official project reference point

The reviewed coordinate supports project navigation near Dahanu. It is not a port limit, cadastral parcel, construction footprint, route, or surveyed centre.

Money meanings stay separate

₹76,220 crore is the Cabinet-approved whole-project total including land acquisition. ₹1,648 crore excluding GST is one package award against a ₹1,770 crore excluding GST package estimate.

Exact organization roles

VPPL remains the project SPV; JNPA and MMB retain their published 74% and 26% shareholding roles; ITD Cementation is the EPC contractor only for the named package.

Cost boundary: the package estimate and package award are compatible with each other but are not whole-project original or revised costs. No actual, final, expenditure, payment, or whole-project award value is inferred.

Lifecycle boundary: Cabinet approval and a dated package award establish the reported project stage through 31 December 2024. They do not establish physical progress, completion, commissioning, inauguration, opening, or current operation.

Coverage boundary: this resolves the held Vadhavan development-project candidate from the major-port lane. Galathea Bay remains held, and the separately modelled NHAI connectivity records remain distinct.

Release 93

A compact default discovery response without losing individual projects

The default 10,004-record map no longer receives a redundant list of all 10,004 record IDs from D1. The already loaded spatial index applies the truthful non-toll catalog scope locally, while filtered, searched, and awareness states continue receiving exact explicit identities.

88% smaller default response

The reviewed first response falls from 301,263 bytes to 35,482 bytes while retaining counts, facets, 24 result rows, toll scope, cursors, freshness, and match reasons.

All 10,004 default records remain individual

The compact scope means every non-toll spatial-index record, not a cluster, count marker, sample, or moved coordinate.

Filtered truth remains explicit

Search, category, state, evidence, lifecycle, precision, organization, mining, attention, and awareness filters still return the exact matching record IDs.

Backward-compatible API

Callers that do not request compact activation continue receiving the complete ordered ID contract from the same versioned endpoint.

Serving boundary: compact activation is allowed only when the discovery layer is All records and no filter or search changes membership. Toll opt-in selects the complete reviewed catalog scope. Any narrower state falls back to explicit IDs.

Truth boundary: the catalog, category, lifecycle, evidence, money, schedule, organization, coordinate, precision, marker, icon, selected dossier, and default toll meanings do not change.

Remaining scale boundary: broad filtered searches can still return large explicit-ID sets. Later viewport activation must preserve exact counts, accessible directory access, source coordinates, and every individual unclustered record.

Release 92

Production D1 discovery with automatic static fallback

The public catalog remains 10,093 source-backed records. Filtered browse, facets, awareness questions, toll opt-in, and cursor pages now use a version-gated D1 read model when healthy, without changing the map, evidence, taxonomy, icons, or selected-project dossiers.

10,093-row discovery projection

Five idempotent migration shards add only the fields needed for filtering, ordering, concise result presentation, and parity checks.

Automatic truthful fallback

A missing binding, stale data version, or failed D1 query returns the same reviewed static discovery contract with a classified read-source header.

Ten parity states

Default, category/state, awareness, toll, evidence, precision, mining, lifecycle, and cursor responses match the validated static model exactly.

One state-link defect repaired

A multi-state NHAI record missing from the normalized D1 state relation is restored idempotently without changing its source wording, coordinates, or project identity.

Serving boundary: D1 becomes primary only when its discovery model reports the exact public data version. Static search, results, selected-record detail shards, evidence, and map-failure access remain independently available.

Scale boundary: this release removes the routine 23.9 MB server-side current-facts fetch from healthy filtered discovery. It still returns the complete active ID set for individual unclustered map activation; viewport query and full-text search remain later scale work.

Truth boundary: no project, coordinate, category, lifecycle, money, schedule, organization role, evidence field, toll default, icon, or dossier content changes in this release.

Release 91

Ten thousand core infrastructure records

The public catalog expands to 10,093 source-backed records and crosses the inventory milestone with 10,004 core non-toll projects, packages, assets, and source-defined systems.

10,004 core records

The 89 reviewed toll-plaza facilities remain separately reported and available only through their explicit opt-in layer.

260 road-and-rail additions

The batch accepts 129 ABSS station developments and 131 NHAI roads or packages from previously held source candidates.

All 438 candidates stay auditable

The ledger records 260 accepted, two duplicate, and 176 needs-review dispositions with reasons and source fingerprints.

36 normalized State/UT facets

Discovery labels now resolve legacy West Bengal and Dadra and Nagar Haveli and Daman and Diu spelling variants without rewriting source wording.

Truth boundary: official Ministry of Railways and NHAI records establish identity and dated source status. GeoNames and OpenStreetMap provide representative navigation only and do not establish project geometry, present operation, award, contractor, cost, schedule, or progress.

Relationship boundary: four source-named NHAI packages link to a broader parent scope only where the published names and chainages support the relationship. Unresolved phase, overlap, and duplicate questions remain held.

D1 and serving boundary: two idempotent migration shards preserve the 438-row control plane, two duplicate decisions, four relationships, and 260 baseline records. Ordered-query parity matches the static fallback across catalog, default scope, state, category, lifecycle, evidence, awareness, and search queries.

Next phase: the numeric inventory milestone is a foundation, not a completeness claim. Source refresh, underrepresented categories, stronger geometry, responsible roles, contracts, money, schedules, audits, and deeper evidence continue.

Release 90

One thousand six hundred eighty-one AMRUT projects with exact-name locality navigation

The public catalog expands to 9,833 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

9,744 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 256 accepted core records remain.

1,681 projects across 25 states and UTs

The batch adds 1,606 Water Supply and 75 Sewerage or Septage records from 1,099 exact-matched official ULB pages.

All 7,612 residual candidates stay auditable

The cumulative ledger retains 1,881 accepted, 1,303 needs-review, and 4,428 pending dispositions without fuzzy substitutions.

Official identity and navigation stay separate

The Ministry directory remains project evidence. GeoNames supplies 1,098 distinct representative locality features under CC BY 4.0.

Truth boundary: portal Project Cost remains its own source-defined quantity, and an undated milestone is not carried forward as current construction, completion, commissioning, inauguration, opening, or operation.

Spatial boundary: acceptance requires one exact normalized primary-or-alternate-name GeoNames place feature in the official source state. A locality point is not a project site, facility, service area, network, route, parcel, or surveyed extent. Barrackpore and North Barrackpore share one source feature without merging their official identities or moving the point.

D1 and serving boundary: eight idempotent migration shards add the 1,681 baseline records, preserve all residual dispositions, and normalize separate official AMRUT and GeoNames source links. Static browse, selected-record evidence, and map-failure access remain independent fallbacks.

Remaining gap: 9,744 core records represent 97.44% of the 10,000-record target. Another 256 accepted core projects or infrastructure assets are required. The held or unsupported AMRUT rows will not be used merely to close that gap.

Release 89

Thirty-eight historical CEA generation assets with conservative representative navigation

The public catalog expands to 8,152 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

8,063 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 1,937 accepted core records remain.

38 representative power-plant points

The accepted assets span 17 states and retain one unique, source-state-contained, fuel-compatible OpenStreetMap navigation match.

All 110 re-review candidates stay auditable

The Release 89 ledger retains 38 accepted and published dispositions and 72 needs-review dispositions.

Historical generation stays historical

Positive January 2024 generation does not establish present operation, current capacity, ownership, commissioning, construction, or performance.

Truth boundary: CEA establishes the station identity and January 2024 observation. It publishes no coordinate in this table. The map point comes from a separately attributed ODbL OpenStreetMap feature and remains representative rather than official or exact.

Selection boundary: acceptance requires a unique named power-plant feature in the independently verified source state, compatible fuel, a normalized match score of at least 0.70, a margin of at least 0.15 over the next candidate, and no high-confidence current-catalog match. The other 72 candidates remain held rather than receiving weak or invented geography.

D1 and serving boundary: one idempotent migration shard adds 38 baseline records and all 110 candidate dispositions. Static browse, selected-record evidence, and map-failure access remain independent fallbacks.

Remaining gap: 8,063 core records represent 80.63% of the 10,000-record target. Another 1,937 accepted core projects or infrastructure assets are required.

Release 88

Two hundred more reviewed AMRUT 2.0 projects from proven locality anchors

The public catalog expands to 8,114 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

8,025 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 1,975 accepted core records remain.

200 individual projects across 18 states and UTs

The deterministic batch adds 100 Water Supply and 100 Sewerage or Septage records using 112 locality anchors already reviewed for Release 79.

All 7,612 residual candidates remain auditable

The checkpoint marks 200 accepted and published while 7,412 remain pending. Shared ULB anchors stay source-locked and are never jittered.

Cost, milestone, and location meanings stay literal

Portal Project Cost remains its own quantity, the directory milestone remains undated, and each marker is a representative locality rather than a project site.

Truth boundary: Release 88 reuses the frozen AMRUT 2.0 directory and reviewed source semantics from Release 79. It does not turn portal Project Cost into original, sanctioned, revised, awarded, paid, actual, or final cost, and it does not carry an undated milestone forward as current construction, completion, commissioning, or operation.

Spatial boundary: the Ministry directory publishes no project coordinate or geometry. Each record uses a separately attributed locality representative already reviewed for its ULB and state. Shared coordinates remain explicit; no site, treatment plant, pipe, sewer, service area, parcel, or route is invented.

D1 and serving boundary: three idempotent migration shards add 200 baseline records and preserve all 7,612 residual candidate dispositions. The compact spatial index, cursor discovery path, selected-record detail shards, and static failure fallback remain independently usable.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1280, 1440, and 1920 pixels without page-level horizontal overflow or browser console errors. The 8,025-record default non-toll scope, 8,114-record catalog, Pandameru-3 search and selection, representative-locality wording, ₹4.74 crore portal Project Cost boundary, Back and Home continuity, phone detail sheet, tablet selected-marker framing, pan, zoom, India reset, and deliberately blocked-basemap directory remained usable.

Remaining gap: 8,025 core records represent 80.25% of the 10,000-record target. Another 1,975 accepted core projects or infrastructure assets are required. This reviewed-anchor batch is not a complete current national water or sewerage inventory.

Release 87

Three hundred five civic-utility facilities from Smart Cities open data

The public catalog expands to 7,914 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,825 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,175 accepted core records remain.

305 individual official facility points

The bounded batch adds 129 Power Grid & Storage, 91 Environmental Utilities, 83 Water System, and two Urban Infrastructure records across nine states and union territories.

All 448 source rows stay auditable

The ledger retains 305 accepted, 91 needs-review, five duplicate, and 47 rejected or deferred dispositions across 28 frozen open-data resources.

Facility identity and dated evidence stay literal

A row establishes a source-listed facility and, where published, a commissioning year. It does not establish present operation, current condition, ownership, performance, or a surveyed parcel.

Truth boundary: the source resources are city asset inventories rather than current operational registers. Release 87 reports Listed in dated city inventory or Commissioning year published; it does not convert a historical listing or year into present operation, continuous service, ownership, capacity, progress, completion, or performance.

Spatial boundary: accepted coordinates are published facility points displayed in WGS 84 longitude-latitude order. Every accepted point matches its declared state and one district, but the point is not upgraded into a surveyed parcel, building footprint, service area, pipe, cable, network, or municipal boundary. Three independently detected state conflicts remain needs review without moving coordinates.

D1 and serving boundary: one idempotent migration shard adds 305 baseline records, all 448 candidate dispositions, five explicit duplicate decisions, 305 typed source-row observations, exact resource links, and official facility-point spatial records. Static browse and evidence reads remain the independent fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1280, 1440, and 1920 pixels without page-level horizontal overflow or browser console errors. The 7,825-record default non-toll scope, 7,914-record catalog, Sanjay Place CWR search and selection, official-facility precision wording, category filters, toll opt-in, Back and Home continuity, phone detail sheet, tablet workspace, selected-marker framing, zoom and Reset to India controls, and deliberately blocked-basemap directory remained usable.

Remaining gap: 7,825 core records represent 78.25% of the 10,000-record target. Another 2,175 accepted core projects or infrastructure assets are required. This bounded nine-state civic-utility source lane is not a complete national utility inventory.

Release 86

Thirty-four BharatNet State/UT systems with source-dated service-ready counts

The public catalog expands to 7,609 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,520 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,480 accepted core records remain.

34 individual Digital & Telecom systems

Each record represents one source-published State/UT scope within BharatNet and uses a separately attributed administrative navigation anchor.

All 34 source rows stay auditable

The complete Annexure-I table is accepted without duplicate inflation. Delhi and Chandigarh are not invented because the source does not publish rows for them.

Counts, roles, and relationships stay literal

Service-ready points, GPs or equivalents, exact organization roles, and the shared national-programme relationship retain their source meanings.

Truth boundary: service-ready points are not unique GPs, routes, towers, exchanges, contracts, completion percentages, commissioned networks, operating connections, or performance verdicts. State-specific money, contractors, present operation, and completion remain not published.

Spatial boundary: the annexure publishes no physical coordinate or network geometry. Survey of India cartographic State/UT label placements are administrative navigation anchors only. Four sit outside the independent land polygons and Puducherry intersects Tamil Nadu; all discrepancies remain explicit without moving coordinates.

D1 and serving boundary: one idempotent migration shard adds 34 baseline records, all 34 candidate dispositions, shared programme relationships, typed count observations, 68 exact organization-role rows, official source links, and administrative spatial records. Static browse and evidence reads remain the independent fallback.

Rendered review: the exact production build was checked at 320, 390, 820 portrait, 1,180 landscape, 1,280, 1,440, and 1,920 pixels. BharatNet search returned all 34 State/UT systems, the compact Project Brief kept its administrative precision and source gaps, Back restored the search, Home restored the clean 7,520-record non-toll scope, and a blocked basemap still left search and all 24 first-page records usable without horizontal overflow or browser errors.

Remaining gap: 7,520 core records represent 75.2% of the 10,000-record target. Another 2,480 accepted core projects are required. This source establishes State/UT system scopes, not a physical inventory of every BharatNet facility or route.

Release 85

Thirty-six Namami Gange sewerage projects with historical status and separated money meanings

The public catalog expands to 7,575 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,486 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,514 accepted core records remain.

36 individual Environmental Utilities records

Five states gain source-named sewerage-project records, each mapped only to a separately attributed representative locality.

All 41 source rows stay auditable

The ledger retains 36 accepted, two duplicate, and three needs-review dispositions. Ambiguous localities do not receive invented points.

Historical status and money stay literal

The 31 December 2021 status cutoff, approved project cost, cumulative expenditure, capacity, approval dates, and completion wording retain their exact source meanings.

Truth boundary: Completed, Completed under O&M, Under Progress, tendering, and AA&ES wording are dated source observations and are not carried forward as current 2026 status. Approved project cost is not revised or final cost, and cumulative expenditure is not treated as a compatible cost revision or contractor payment.

Spatial boundary: the annexure publishes no project coordinate or geometry. Each accepted record uses a separately attributed OpenStreetMap locality representative, never an STP site, sewer or drain alignment, footprint, parcel, service area, or surveyed project extent.

D1 and serving boundary: one idempotent migration shard adds 36 baseline records, all 41 dispositions, two deduplication decisions, exact source links, typed status and row-field observations, source-reporting-ministry roles, and representative spatial records. Static browse and evidence reads remain the independent fallback.

Rendered review: the exact production build was reviewed at 320 and 390 phone widths, 820 tablet portrait, 1180 landscape, 1440, and 1920 pixels without page-level horizontal overflow or browser console errors. It verified the 7,486-record default non-toll scope, 436-record Environmental Utilities facet, Joshimath search and selection, compact Project Brief, approved cost and cumulative expenditure as separately typed money, representative-locality wording, selected-marker framing, Home reset, pan, zoom, India reset, phone and tablet detail, and a deliberately blocked-basemap directory.

Remaining gap: 7,486 core records represent 74.86% of the 10,000-record target. Another 2,514 accepted core projects are required. This five-state historical annexure is a bounded source lane, not a current national wastewater inventory.

Release 84

One hundred sixteen major railway projects from a Ministry of Railways/PIB source lane

The public catalog expands to 7,539 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,450 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,550 accepted core records remain.

116 individual Railway records

Twenty records are anchored in Bihar, 23 in Gujarat, 34 in Madhya Pradesh, and 39 in Uttar Pradesh, with cross-state source scope retained where the same project appears in multiple tables.

All 163 source rows stay auditable

The ledger retains 116 accepted, 33 duplicate, and 14 needs-review dispositions. Unresolved rows do not receive an invented point or catalog count.

Status and money meanings stay literal

Completed, Taken up, Works taken up, Recently sanctioned, Cost, and Latest Cost retain the Ministry's table meanings rather than becoming operation, construction, progress, or final-cost claims.

Spatial boundary: the PIB tables publish no reusable coordinate or railway alignment. Each accepted record uses a separately attributed OpenStreetMap named endpoint or locality whose own address passed India and source-state review. No route, midpoint, worksite, parcel, project boundary, or surveyed extent is invented.

D1 and serving boundary: one idempotent migration shard adds 116 baseline records, all 163 dispositions, 33 deduplication decisions, exact source links, typed status and row-field observations, source-reporting-ministry roles, and representative spatial records. Static browse and evidence reads remain the independent fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1024, 1180 landscape, 1280, 1440, and 1920 pixels without page-level horizontal overflow or browser console errors. Railway search, the 1,448-record Railway facet, Araria-Galgalia selection, compact Project Brief, literal project-cost wording, official evidence access, selected-marker framing, phone sheet, tablet workspace, default non-toll scope, and map-independent directory remained usable. A local wide-screen run painted the first real project markers at 590 ms and reported LCP at 296 ms; these are release evidence, not a public p75 claim.

Remaining gap: 7,450 core records represent 74.5% of the 10,000-record target. Another 2,550 accepted core projects are required. The four-state parliamentary answer is a bounded source lane, not an all-India railway inventory.

Release 83

One hundred eighty-one NHAI national-highway projects and packages

The public catalog expands to 7,423 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,334 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,666 accepted core records remain.

181 individual road records

One hundred thirty-seven national-highway projects and 44 separately identified packages remain individually searchable, filterable, and mapped as Major records.

All 821 source rows stay auditable

The ledger retains 181 accepted, nine duplicate, 38 needs-review, 224 pending-navigation, and 369 rejected or deferred dispositions.

Planning and procurement semantics stay literal

Balance For Award, intended mode, total length, and DPR Name do not become award, contract, construction, completed length, contractor, consultant, progress, or operation claims.

Spatial boundary: the NHAI report publishes no reusable coordinate or route geometry. Each accepted record uses a separately attributed OpenStreetMap place or administrative representative. No alignment, chainage, package midpoint, worksite, land boundary, or surveyed extent is invented.

D1 and serving boundary: one idempotent migration shard adds 181 baseline records, all 821 dispositions, nine deduplication decisions, exact source links, field observations, source-publisher roles, and representative spatial records. Fourteen ordered query sets retain exact D1-to-static parity while static browse and evidence reads remain the independent fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels without page-level horizontal overflow or browser console errors. The 7,334-record default non-toll scope, 719-record Highway / Road facet, NHAI search and selection, compact Project Brief, representative-point wording, shareable filter URL, clean Home reset, and map-independent directory path remained usable while the accepted freestanding pictograms, selected-marker framing, and existing workspace behavior stayed unchanged.

Remaining gap: 7,334 core records represent 73.34% of the 10,000-record target. Another 2,666 accepted core projects are required, with category and state balance still governed by the inventory coverage matrix.

Release 82

Seventeen unique NICDC industrial-corridor projects after canonical deduplication

The public catalog expands to 7,242 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,153 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,847 accepted core records remain.

17 individual industrial-corridor projects

The Industrial Corridor category grows from eight to 25 records across 12 states. Every accepted record remains individually searchable and mapped.

All 27 project sections stay auditable

Seventeen accepted records and ten reviewed links to existing canonical projects retain their dispositions, source pages, fingerprints, and review reasons in D1.

Stage, area, and roles stay literal

Source-dated stage wording, typed planning or project areas, and exact SPV or delivery roles do not become present status, surveyed polygons, whole-project completion, operation, or one synthetic cost.

Spatial boundary: NICDC publishes no reusable project coordinates or geometry in the reviewed report. Sixteen projects use separately attributed locality representative points. The Jharkhand record remains unresolved at state level because the report says an alternate site is being identified. None is presented as a project site, land boundary, route, or surveyed extent.

D1 and serving boundary: one idempotent migration shard adds 17 baseline records, all 27 candidate dispositions, ten source-to-canonical links, exact organization roles, typed stage and area observations, and spatial-source links. Thirteen ordered query sets retain exact D1-to-static parity while static browse and evidence reads remain the independent fallback.

Rendered review: the exact production build passed the selected-project flow at 320, 390, 820 portrait, 1180 landscape, 1280, 1440, and 1920 pixel widths without page-level horizontal overflow or a workspace-hidden marker. The first real project markers appeared in about 451 ms in the local 1440-pixel review; this is build evidence, not a production percentile or a claim that every device meets the long-term performance budget.

Remaining gap: 7,153 core records represent 71.53% of the 10,000-record target. Another 2,847 accepted core projects are required, with category and state balance still governed by the inventory coverage matrix.

Release 81

Fifteen prioritised multimodal logistics parks

The public catalog expands to 7,225 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,136 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,864 accepted core records remain.

15 individual MMLP projects

Six source-dated implementation records and nine DPR or appraisal records remain searchable as Logistics & Inland Transport projects.

The complete source table is auditable

All 15 official rows passed identity, category, state, locality, bounds, containment, and duplicate review with no unresolved or duplicate candidate.

Truth boundary: the Ministry's 1 April 2026 Parliament answer supports named MMLP identities, locations, a dated implementation or DPR state, and authority-estimated cargo capacity for four rows. It does not establish present-day status, exact sites, cost, contractor, concessionaire, physical progress, completion, operation, or performance.

Spatial boundary: the answer publishes no coordinate or geometry. Each record uses a separately attributed OpenStreetMap city or locality representative point, never the MMLP site, facility extent, transport connection, land parcel, or surveyed position.

D1 and serving boundary: one idempotent migration shard adds 15 baseline records, all candidate dispositions, exact reporting-ministry roles, dated status observations, source links, and representative spatial records. Static browse and evidence reads remain the independent public fallback.

Remaining gap: 7,136 core records represent 71.36% of the 10,000-record target. Another 2,864 accepted core projects are required.

Release 80

Fifty-six reviewed PNGRB pipeline assets

The public catalog expanded to 7,210 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,121 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,879 accepted core records remained.

56 individual pipeline assets

Thirty-three natural-gas and 23 petroleum-product pipeline identities remain individually searchable and mapped through conservative representative points.

All 65 source rows stay auditable

Fifty-six accepted records and nine source-to-canonical duplicate links retain their dispositions, fingerprints, and review reasons in D1.

Truth boundary: PNGRB's March 2026 physical-state tables and April 2026 monthly observations are dated evidence, not present-day status. The source column named Entity remains PNGRB-reported entity, not contractor, operator, owner, sponsor, concessionaire, or authority. Representative endpoint and administrative anchors are not pipeline routes, stations, rights of way, or surveyed geometry.

D1 and serving boundary: one idempotent migration shard adds 56 baseline records, all 65 candidate dispositions, nine deduplication decisions, exact source roles, typed physical and monthly observations, source links, and representative spatial records. Thirteen ordered query sets retain exact D1-to-static parity, while static browse and evidence reads remain the independent public fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1440, and 1920 pixels. The 7,121-record default non-toll directory, 126-record Pipelines & Fuel facet, a representative PNGRB Project Brief, exact organization-role wording, Back-state continuity, clean Home reset, source-locked freestanding icons, and deliberately blocked-basemap fallback remained usable without page-level horizontal overflow or browser warnings. A combined drag and wheel sample held 60.1 frames per second.

Remaining gap: 7,121 core records represented 71.21% of the 10,000-record target. Another 2,879 accepted core projects were required, with category and state balance still governed by the inventory coverage matrix.

Release 79

Five hundred state-balanced AMRUT 2.0 water and sanitation records

The public catalog expands to 7,154 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

7,065 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Another 2,935 accepted core records remain.

500 individual baseline records

Two hundred and fifty Water Supply and 250 Sewerage or Septage records span 31 states and union territories. Every record remains individually searchable and mapped.

All 8,769 source rows stay auditable

The refreshed Ministry directory records 500 accepted, 353 already published, 304 needs-review, and 7,612 pending dispositions. Twenty-one changed source rows remain explicit revisions.

Source meanings remain literal

Project Cost and an undated portal milestone are not relabeled as sanctioned cost, award, expenditure, current progress, completion, or final cost.

Spatial boundary: the Ministry pages name ULBs but publish no project coordinate or geometry. The 500 projects use 374 separately attributed representative locality anchors. Shared anchors are preserved without jitter and do not imply project-site precision.

Review boundary: three unresolved ULB navigation gaps remain needs-review rather than receiving guessed coordinates. Smart Cities and PMGSY source paths did not meet this release's reproducible public-access contract and contributed no records.

D1 and serving boundary: four idempotent migration shards retain the exact 500 project identities and the complete 8,769-row candidate ledger. Twelve ordered query sets preserve D1-to-static parity while static browse and evidence reads remain the independent fallback.

Remaining gap: 7,065 core records represent 70.65% of the 10,000-record target. The next lane should improve transport, logistics, industrial, digital, pipeline, or environmental category balance rather than repeatedly selecting from the same urban-water source.

Release 78

Forty-seven under-construction TBCB transmission projects after cross-catalog deduplication

An eleventh auditable source lane expands the public catalog to 6,654 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

6,565 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

47 individual transmission projects

Every accepted record remains a Power Grid & Storage project with a source-named representative corridor anchor. No project receives an invented route, substation point, or exact geometry.

All 86 source rows stay auditable

D1 records 47 accepted projects and 39 reviewed links to existing PAIMANA canonical records. Duplicate source rows do not inflate the public catalog.

Lifecycle, schedule, and money stay literal

May 2026 under-construction classification, original and anticipated targets, exact Executing Agency role, and Cost (Rs. Cr) remain separate source meanings rather than a present-status, overrun, final-cost, or synthetic-progress claim.

Source boundary: the CEA May 2026 TBCB report is indicative and states that it must not be used as a ground to claim time or cost overrun. Its 301 component rows have different physical denominators and are not averaged into one whole-project progress percentage.

Spatial boundary: the report publishes no reusable coordinate or line geometry. Forty-seven projects use 41 separately attributed representative OpenStreetMap anchors from source-named places. These are not CEA coordinates, substations, towers, rights-of-way, surveyed alignments, or complete project extents.

D1 and serving boundary: one idempotent migration shard adds 47 accepted records, the complete 86-row disposition ledger, 39 deduplication decisions, typed cost and schedule observations, exact Executing Agency roles, source-dated lifecycle events, source links, and representative spatial records. Twelve ordered query sets retain exact D1-to-static parity, while static browse and evidence reads remain the independent public fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1280, and 1920 pixels. The 6,565-record default non-toll directory, a distinctive new TBCB search, representative selected-marker framing, compact Project Brief, typed Money view, Back-state continuity, clean Home reset, optional toll layer, and deliberately blocked-basemap fallback remained usable without page-level horizontal overflow or browser warnings.

Remaining gap: 6,565 core records represent 65.65% of the 10,000-record target. Another 3,435 accepted core projects are required, with category and state balance still governed by the inventory coverage matrix.

Release 77

Fifty-eight under-construction RTM transmission projects with source-dated lifecycle evidence

A tenth auditable source lane expanded the public catalog to 6,607 source-backed records without redesigning the accepted map, freestanding pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

6,518 core records toward 10,000

The catalog also preserved 89 toll-plaza facilities behind the explicit opt-in layer.

58 individual transmission projects

Every accepted record remained a Power Grid & Storage project with a source-named representative corridor anchor.

All 70 source rows stay auditable

D1 records 58 accepted projects, six exact catalog duplicates, and six needs-review rows.

Lifecycle, schedule, and money stay literal

May 2026 lifecycle, target months, Executing Agency, and Cost (Rs. Cr) retain their exact source meanings.

Source boundary: the CEA report is indicative and states that it must not be used as a ground to claim time or cost overrun. Component indicators with different denominators are not averaged into synthetic whole-project progress.

Spatial boundary: 58 projects use 47 separately attributed representative anchors, not CEA coordinates, exact substations, routes, towers, or project extents.

Release 76

Seventy-eight completed-TBCB transmission projects with typed schedule evidence

A ninth auditable source lane expands the public catalog to 6,549 source-backed records without redesigning the accepted map, pictograms, discovery workspace, compact Project Brief, optional toll layer, or specialist evidence model.

6,460 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

78 individual transmission projects

Every accepted record remains a Power Grid & Storage project with a source-named representative corridor anchor. No project receives an invented route, substation point, or exact geometry.

All 79 source rows stay auditable

D1 records 78 accepted projects and one Nangalbibra or Nongalbibra needs-review candidate whose navigation evidence did not pass the state-validity gate.

Schedule and money stay literal

Original scheduled COD, actual COD, deterministic month difference, exact Executing Agency role, and Cost (Rs. Cr) remain separate source meanings rather than an overrun, final-cost, or current-operation claim.

Source boundary: the CEA May 2026 completed-TBCB report is indicative and states that it must not be used as a ground to claim time or cost overrun. Completed and Actual COD do not establish present operation, availability, ownership, asset condition, utilization, or benefit realization.

Spatial boundary: the report publishes no reusable coordinate or line geometry. Seventy-eight projects use 57 separately attributed representative OpenStreetMap anchors from source-named places. These are not CEA coordinates, substations, towers, rights-of-way, surveyed alignments, or complete project extents.

D1 and serving boundary: one idempotent migration shard adds 78 accepted records, the complete 79-row disposition ledger, typed cost and schedule observations, exact Executing Agency roles, lifecycle events, source links, and representative spatial records. Twelve ordered query sets retain exact D1-to-static parity, while static browse and evidence reads remain the independent public fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels. The 6,460-record default non-toll scope, 131-record Power Grid & Storage facet, CEA Project Brief, typed Timeline and Evidence views, clean Home reset, selected-marker framing, and deliberate basemap-failure directory remained usable without page-level horizontal overflow or browser console errors.

Remaining gap: 6,460 core records represent 64.6% of the 10,000-record target. The separately staged CEA under-construction RTM and TBCB reports are not part of this release and require their own identity, spatial, lifecycle, schedule, and disclaimer review.

Release 75

Freestanding category pictograms replace circular marker medallions

The map now gives every infrastructure category a fuller, clearer icon-first identity without changing any record, category assignment, coordinate, evidence field, filter, lifecycle, URL, dossier, toll default, or D1 inventory rule.

Sixteen freestanding pictograms

A reviewed Lucide-based asset registry generates stable category-colored icons with a silhouette-following warm-white contour and restrained shadow. No permanent circle, square, diamond, or capsule encloses the category icon.

Precision remains independent

Short solid, double, dotted, tailed, mine-representative, and unresolved marks preserve exact, official-facility, locality, corridor, and conflict meaning without moving or upgrading a point.

One identity across the product

The same icon and color now appear in native map symbols, filters, results, previews, the map key, Project Briefs, and existing category-bearing surfaces. Selection uses a temporary silhouette-following neutral outline.

Release 74 data stays intact

All 6,471 records, 6,382 core projects or assets, 89 opt-in toll plazas, eight D1 source ledgers, twelve parity checks, and progressive selected-record shards remain unchanged.

Subtype boundary: irrigation, renewable generation, data-centre, telecom or fibre, and submarine-cable variants are presentation-only within their canonical category. A variant activates only from a reviewed source-type or sector field, never from cost or a vague name. Unsupported variants remain dormant.

Performance boundary: markers remain native MapLibre symbols with feature-state interaction, source-locked coordinates, larger invisible hit targets, deterministic draw priority, no DOM markers, no clusters, no jitter, and no positional transition. The small real-point fallback remains available if an icon asset fails.

Visual boundary: the supplied full-resolution concept is art direction only. The shipped assets are generated from the maintained professional vector family rather than cropped from the poster, and the poster contributes no project data or taxonomy fact.

Release 74

1,095 railway-station development records from a complete national scheme list

An eighth auditable source lane expands the public catalog to 6,471 source-backed records without redesigning the accepted map, discovery workspace, Project Brief, optional toll layer, or specialist evidence model.

6,382 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

1,095 individual station developments

Every accepted record retains its official Ministry station identity and a separately attributed representative station point. They appear in the default non-toll All-records view and Facilities layer, while the Major-project layer remains unchanged.

All 1,309 source positions remain auditable

D1 records 1,095 accepted, 71 needs-review, and 143 pending candidates. Three source-count gaps, ambiguous names, state conflicts, and five possible existing-project overlaps remain held.

141 dated completion observations

The 12 March 2026 Ministry update supports completion for 141 accepted records. The other 954 retain only the 8 December 2023 identification state and an explicit newer-evidence warning.

Source boundary: the Ministry of Railways list published through PIB supplies station identity, state, scheme inclusion, and the source total. A later PIB list supplies the dated completion observation for matched station names. Neither source supplies station-level cost, contractor, tender, schedule, exact works, present operation, or universal current progress.

Spatial boundary: frozen Wikidata CC0 railway-station points are used only after exact normalized label or alias matching, India bounds, unique-item review, and independent state containment. A representative point is not an official Railway coordinate, station boundary, platform, parcel, construction worksite, or project footprint.

Lifecycle boundary: identified, completed, commissioned, inaugurated, opened, and presently operating remain different states. Completion is shown only for the 141 exact reviewed crosswalks; the absence of a station from the later 180-name completion list is not treated as proof that it remains incomplete.

D1 and serving boundary: five idempotent migration shards add 1,095 accepted records, the complete 1,309-position candidate ledger, typed lifecycle observations, exact scheme-ministry roles, navigation evidence, aliases, maturity rows, and source links. Static browse and evidence reads remain the independent public fallback.

Scale correction: the first saved deployment candidate failed safely before replacing production because the 50,513,456-byte worker exceeded the platform startup CPU budget. Full selected-record data now lives in 256 deterministic, on-demand static shards. The exact replacement worker is 734,512 bytes, while all 6,471 records, Project Briefs, specialist sections, evidence, and fallback paths remain intact.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels. The 6,382-record default non-toll scope, unchanged Major-project layer, Facilities, Railway filtering, station search, Project Briefs, clean Home reset, phone detail sheet, tablet selected-marker framing, and static map-failure access remained usable without page-level horizontal overflow or browser console errors.

Remaining gap: 6,382 core records represent 63.82% of the 10,000-record target. Seventy-one ABSS candidates still need adjudication and 143 need stronger reusable navigation evidence. Large permission-cleared road, rail-project, logistics, industrial, grid, digital, urban, and environmental inventories remain the broader coverage bottleneck.

Release 73

Sixty-eight National Waterway systems with strict representative geography

A seventh auditable source lane expands the public catalog to 5,376 source-backed records without redesigning the accepted map, discovery workspace, Project Brief, optional toll layer, or specialist evidence model.

5,287 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

68 individual waterway systems

Every accepted system uses a separately attributed named-waterbody representative point. No candidate receives an invented centroid, route, or exact geometry.

All 111 candidates remain auditable

D1 records 68 accepted baseline systems and 43 needs-review candidates whose navigation evidence did not pass the strict hydronym, source-state, and India-bounds checks.

Designation stays separate from operation

A listed or declared National Waterway does not establish current navigability, traffic, construction, completion, commissioning, opening, cost, schedule, or present condition.

Source boundary: the Ministry's National Waterways list supplies the stable identity, component descriptions, published component lengths, and state scope. The National Waterways Act, 2016 supplies the statutory boundary. Neither supplies current operational evidence or a reusable route dataset.

Spatial boundary: cached OpenStreetMap Nominatim results under ODbL supply only separately attributed representative navigation points on one named component. No point is an official Ministry coordinate, waterway centre, endpoint, surveyed site, channel limit, navigable extent, complete route, or proof of operation.

Entity boundary: National Waterway systems remain separate from development works on those systems. National Waterway 1 is linked to Jal Marg Vikas without merging identities or transferring lifecycle, money, schedule, organization, progress, or geometry claims.

D1 and serving boundary: the incremental idempotent migration adds 68 accepted records, the full 111-row ledger, two fingerprinted official sources, 204 source links, 136 typed observations, exact source-publisher roles, aliases, and the reviewed NW-1 relationship. Static browse and evidence reads remain the independent public fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels. The 5,287-record default non-toll directory, 72-record Logistics & Inland Transport facet, National Waterway search and Project Brief, clean Home reset, phone detail sheet, tablet selected workspace, and static map-failure access remained usable without page-level horizontal overflow or browser console errors.

Remaining gap: 5,287 core records represent 52.87% of the 10,000-record target. Forty-three National Waterway candidates still need stronger reusable geography, while permission-cleared railway, road, logistics, industrial, grid, digital, and environmental inventories remain the larger scale bottleneck.

Release 72

Twelve operational major-port assets with dated cargo evidence

A sixth auditable source lane expands the public catalog to 5,308 source-backed records without redesigning the accepted map, discovery workspace, Project Brief, optional toll layer, or specialist evidence model.

5,219 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

12 individual major-port assets

Nine use official port-table reference points. Deendayal, Mumbai, and Syama Prasad Mookerjee retain representative anchors because the source describes multi-location port systems.

All 14 designated ports remain auditable

D1 records 12 accepted operational assets and two needs-review construction candidates. Vadhavan and Galathea Bay are not forced into the published count.

Operational scope stays dated

Positive May 2026 cargo supports a source-dated operational observation. It does not establish uninterrupted current operation, capacity, service quality, ownership, completion, commissioning, or present condition.

Source boundary: the Ministry's Basic Port Statistics 2024-25 supplies the major-port identity and topography references. The May 2026 cargo report supplies advance-estimate tonnes and the dated operational observation. Neither source supplies a complete port boundary or development-project dossier.

Spatial boundary: the source's degree-minute-second coordinates were normalized into longitude-latitude order for WGS 84 display. The table does not publish its geodetic datum, and its points are not port limits, berth or terminal boundaries, cadastral parcels, surveyed centres, or complete asset extents.

Entity boundary: seven earlier port development projects remain separate from the 12 port assets. Five reviewed asset-to-development-project links are stored without merging terminal, berth, jetty, or pipeline works into their parent port asset.

Containment boundary: five official points fall inside the reviewed land polygons and one district. Seven coastal reference points sit outside the land-only state and district polygons, so the explicit coastal exception remains visible and the points were not moved inland.

D1 and serving boundary: the incremental idempotent migration adds the 12 accepted records, full 14-row candidate ledger, two immutable official documents, 24 source links, 24 field observations, exact authority roles, aliases, and reviewed relationships. Static browse and evidence reads remain the independent public fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels. The 5,219-record default non-toll directory, 19-record Port facet, Chennai Port search and Project Brief, clean Home reset, phone detail sheet, tablet selected workspace, and static map-failure access remained usable without page-level horizontal overflow or browser console errors.

Remaining gap: 5,219 core records represent 52.19% of the 10,000-record target. Large permission-cleared transport, logistics, industrial, grid, digital, and environmental inventories remain the scale bottleneck.

Release 71

One hundred five licensed public-use airport assets

A fifth auditable source lane expands the public catalog to 5,296 source-backed records without redesigning the accepted map, discovery workspace, Project Brief, optional toll layer, or specialist evidence model.

5,207 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

105 individual airport assets

Each asset retains its DGCA identity and licence-validity record, plus a separately attributed representative navigation point. Existing airport development projects remain separate entities.

All 110 candidates remain auditable

D1 records 105 accepted, four needs-review rows, and one earlier Thiruvananthapuram observation linked as a duplicate rather than counted twice.

Licence scope stays literal

A public-use aerodrome licence does not establish current flights, scheduled service, operation, ownership, commissioning, construction completion, capacity, or exact airport geometry.

Source boundary: the DGCA public-use register supplies aerodrome identity, ICAO indicator, licence number, validity dates, and the 17 July 2026 source update. It does not publish state, district, coordinate, geometry, operator, capacity, or present service.

Spatial boundary: 103 points come from a pinned public-domain OurAirports snapshot. Datia and Pantnagar use cached OpenStreetMap Nominatim results under ODbL. Every point remains representative, not a DGCA coordinate, aerodrome reference point, runway point, terminal site, parcel, or airport polygon.

Review boundary: Aizawl and Rewa remain held after their DGCA validity dates passed, Bhogapuram remains held without a licence number or validity dates, and Shravasti remains held because current DGCA and AAI licence identities conflict. Fifteen asset-to-project relationships remain separately reviewable and do not merge the entities.

D1 and serving boundary: an incremental idempotent migration adds the 105 accepted records and complete 110-row ledger. Twelve ordered query sets retain exact D1-to-static parity, while static browse and evidence reads remain the independent public fallback.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels. The 5,207-record default non-toll directory, 130-record Airport facet, Juhu Airport search and Project Brief, clean Home reset, phone detail sheet, tablet selected-marker framing, and static map-failure access remained usable without page-level horizontal overflow or browser console errors.

Remaining gap: the catalog is still water-heavy. Permission-cleared, current transport, logistics, industrial, grid, digital, and environmental inventories with stable identities and reusable geography remain the primary bottleneck.

Release 70

One hundred two historical generation assets from a fourth source lane

A conservative Central Electricity Authority batch expands the public catalog to 5,191 source-backed records without redesigning the map, discovery workspace, markers, Project Brief, optional toll layer, or specialist evidence model.

5,102 core records toward 10,000

The catalog also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Only accepted baseline-or-better non-toll records count toward the inventory target.

102 individual generation assets

Every accepted row has a positive CEA generation observation for January 2024 and a separately attributed representative navigation point. No record is clustered, moved, or given invented site precision.

All 526 candidates remain auditable

D1 records 102 accepted, 46 needs review, 98 hydro rows deferred for NWIC reconciliation, and 280 pending without a conservative coordinate match.

Historical evidence stays historical

Positive January 2024 generation does not establish present operation, ownership, commissioning, current capacity, availability, or performance after the source period.

Source boundary: CEA supplies official station identity, state, fuel grouping, monitored capacity, and dated generation fields through data.gov.in under the Government Open Data License India. The source does not publish coordinates or current lifecycle.

Spatial boundary: Wikidata supplies only a frozen CC0 navigation point after conservative name matching, unique-item review, India bounds, and state containment. It is not an official CEA coordinate, surveyed facility point, plant boundary, unit point, or exact project footprint.

Deduplication boundary: hydro candidates remain deferred until they can be reconciled with existing NWIC powerhouse assets. Development projects and physical station assets remain different entity kinds; no relationship is merged merely from a similar name or nearby point.

D1 and serving boundary: an incremental idempotent migration adds the 102 accepted records and the complete 526-row control ledger. Twelve ordered query sets retain exact D1-to-static parity, while static browse and evidence reads remain the independent public fallback.

Remaining gap: the catalog is still water-heavy, and this CEA source is historical. Current, permission-cleared transport, logistics, industrial, grid, digital, and environmental inventories with stable identities and reusable geography remain the primary bottleneck.

Release 69

Five thousand accepted core records with three auditable source lanes

Two thousand five hundred reviewed additions expand the public catalog to 5,089 source-backed records without changing the accepted map, Project Brief, optional toll layer, evidence semantics, or individual unclustered marker system.

5,000 core records toward 10,000

The checkpoint also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Candidate rows, duplicate sources, review holds, rejected rows, pending rows, and toll plazas do not inflate the core target.

Three bounded source contributions

The release adds 1,873 more NWIC water assets, 309 PAIMANA road or railway projects, and 318 AMRUT 2.0 water-supply or sewerage projects. Each record retains its reviewed identity, source geography, precision, evidence date, and explicit gaps.

17,780 candidate rows remain auditable

D1 retains the complete 7,024-row NWIC, 1,987-row PAIMANA, and 8,769-row AMRUT ledgers with exact dispositions, reasons, source links, fingerprints, aliases, and canonical links.

Current status is not manufactured

The 2022 NWIC inventory is evidence of source-listed assets and points, not present operation. AMRUT projects sharing a reviewed locality anchor remain representative, and PAIMANA rows that failed spatial lookup remain held rather than assigned a fallback coordinate.

Count boundary: the 5,089-record catalog contains exactly 5,000 accepted core projects or infrastructure assets and 89 separately reported toll-plaza facilities. The 2,500 additions are 1,873 NWIC, 309 PAIMANA, and 318 AMRUT records.

Review boundary: NWIC retains 3 duplicates, 184 needs-review rows, and 3,375 pending rows. PAIMANA retains 10 duplicates, 722 needs-review rows, and 94 rejected or deferred rows. AMRUT retains 18 anchor collisions for review and 8,398 pending rows.

Spatial boundary: all 5,089 positions pass independent state and district checks. Twenty-eight source-state differences remain explicit. Kakari Mahudi Dam is returned by both Arvalli and Mahisagar district boundaries, so no district is assigned to that record.

Serving boundary: the complete spatial index is about 8.4 MB uncompressed, while the first 24-row discovery response with 5,000 active IDs is about 130 KB. Removing a shared runtime import of the full source catalog reduces the compiled InfrastructureMap client chunk from 41.3 MB to about 227 KB. D1 imports the three source lanes idempotently and retains exact query parity; static read models remain the independent fallback.

Coverage limitation: all maintained categories and every state or union territory have records, but the checkpoint remains strongly water-heavy and many source dates are stale. Airports, ports, digital, logistics, industry, grid, pipelines, and other network categories need stronger current authoritative inventories before 10,000.

Release 68

Two thousand five hundred core records and a second authoritative source family

One thousand five hundred eighty-nine reviewed National Water Informatics Centre assets expand the public catalog to 2,589 source-backed records without changing the accepted map, Project Brief, filters, optional toll layer, or deeper evidence model.

2,500 core records toward 10,000

The checkpoint also preserves 89 toll-plaza facilities behind the explicit opt-in layer. Candidate rows, duplicate sources, review holds, pending rows, and toll plazas do not inflate the core target.

1,589 new individual assets

The batch adds 221 dams, 282 powerhouses, and 1,086 barrages, weirs, or anicuts. Every feature keeps its official source point, source CRS, WGS 84 transformation, and official-facility precision.

All 7,024 NWIC candidates remain auditable

D1 records 1,589 accepted or published, 3 duplicate, 184 needs review, and 5,248 pending candidate rows alongside the unchanged PAIMANA ledger.

Current status is not inferred

The official resources were updated on 28 September 2022. They establish source-listed assets and reference points, not present operation, ownership, contractor, cost, progress, or conditions after that date.

Source boundary: the three reviewed resources are the OGD Point Layer of Dams of India, Point Layer of Powerhouse, and Point of Barrage, Weir, or Anicut. Archive hashes, byte lengths, source fields, retrieval date, and the Government Open Data License India remain recorded.

Review boundary: coordinate disagreements, JK-coded geography requiring current J&K or Ladakh review, missing state scope, two border-sensitive positions, and unselected source rows remain outside the accepted count. Three source rows are linked as reviewed duplicates rather than double-counted.

Spatial boundary: all 2,589 points pass state and district containment, with 25 source-state differences kept explicit. Containment does not upgrade an official point into a surveyed footprint, reservoir polygon, route, or project extent.

Serving boundary: the 24-row first discovery response is 79.6 KB, under 2% of the full fallback fact index. When more than 1,200 records match, national zoom deterministically prioritizes 700 individual markers through a balanced established-project and baseline-asset mix, then reveals the remainder with zoom or filtering while the exact matching count stays visible. D1 stages both source control planes and twelve exact query checks; versioned static reads remain the independent public fallback.

Coverage limitation: the checkpoint is intentionally source-backed but water-heavy. The next 5,000-record phase must add more authoritative source families and improve category and state balance rather than treating this source distribution as national completeness.

Release 67

One thousand reviewed records and an auditable D1 inventory control plane

Three hundred eighty-two reviewed PAIMANA projects expand the public catalog to 1,000 source-backed records. The accepted interface remains unchanged while the data path now separates broad baseline inventory from selective deep evidence.

911 core projects toward 10,000

The public checkpoint also retains 89 toll-plaza facilities behind the explicit opt-in layer. Candidates, duplicates, deferred rows, and toll plazas do not inflate the core target.

382 new individual records

Separately reviewable source lanes add 208 Highway or Road, 124 Railway, and 50 cross-sector records. Every feature retains its original reviewed coordinate and precision meaning.

All 1,987 source candidates remain auditable

D1 records 852 accepted or published, 10 duplicate, 136 needs review, 94 rejected or deferred, and 895 pending candidate rows with reasons and timestamps.

Inventory maturity stays explicit

The catalog contains 135 baseline, 843 validated-detail, and 22 deep-evidence records. Missing contracts, payments, audits, roles, or geometry remain missing rather than blocking truthful baseline publication.

Count boundary: 1,000 is the complete public catalog count. The 10,000-project objective is at 911 because the 89 reviewed toll plazas remain a separate facility layer.

Source boundary: all additions come from the official May 2026 PAIMANA candidate universe. Sixty-six replacement candidates passed independent state-matched geocoding after earlier candidates failed the spatial gate. No fallback coordinate was invented.

Serving boundary: the public map continues to use compact versioned spatial and discovery reads with static failure fallback. D1 now exposes the candidate ledger, maturity counts, and twelve exact ordered-query parity checks, but full public discovery cutover remains staged.

Next checkpoint: reach 2,500 accepted core projects using more than one major authoritative source family and materially broader category and state coverage.

Release 66

One hundred more reviewed systems and twelve exact D1 query checks

One hundred reviewed central-sector projects expand the public catalog to 618 individual source-backed records. The batch preserves the exact first 370 PAIMANA selections and adds railway systems, national highways, public healthcare and higher-education infrastructure, fuel systems, and steel or mineral-processing development from the same May 2026 official source universe.

470 cumulative PAIMANA records

The batch contains 25 Railway, 20 Highway or Road, 30 Urban Infrastructure, 15 Pipelines and Fuel, and 10 Mine-category development records across 26 state tokens. Every record retains its official identity, source fields, review rule, spatial evidence, and explicit gaps.

618 individual map features

The catalog contains 494 Major projects or mine assets and 124 Facilities or local schemes. The default non-toll scope contains 529 records; all 89 toll plazas remain available through their explicit opt-in layer, direct links, and intentional search.

Spatial review remains attributable

All 618 positions pass independent state and district containment. Six hundred twelve agree with their declared state scope, the same six earlier NHAI conflicts remain explicit, and the positions resolve across 344 district-code pairs.

D1 compares twelve ordered result sets

The staged 618-record import matches the versioned public read model on ordered project IDs and SHA-256 digests, including the newly expanded Railway and Urban Infrastructure categories.

Selection boundary: these 100 records were selected from official sector and physical-scope evidence, reviewable named geography, state balance, and spatial-review readiness. They are not a cost ranking, a complete inventory, or a judgment about unselected projects.

Spatial boundary: representative facility, locality, and corridor anchors remain navigation context, not surveyed sites, alignments, rights of way, project extents, plant boundaries, mine leases, or operating evidence. Twenty-four new and 55 cumulative shared-anchor cases keep every reviewed coordinate unchanged.

Interface boundary: the accepted map, compact Project Brief, filters, optional toll layer, shareable state, and specialist evidence tabs are unchanged. The larger catalog uses the same points-first read path and native individual MapLibre features.

Rendered release gate: the exact build passed the 320, 390, 820, 1180, 1440, and 1920 pixel review with no page overflow, working selected-record and failure paths, and a measured 142 ms first-marker point on local desktop. The five-million-row local SQLite metadata benchmark retained single-digit-millisecond query times; neither measurement is presented as production D1 latency.

Still incomplete: 1,517 PAIMANA source rows remain unselected. Many need stronger entity resolution, supported geometry, or package-versus-project review. D1 remains a shadow read model; R2, PMTiles, full-text search, production-like concurrency evidence, and a public database read cutover remain future scale work.

Release 65

Fifty more reviewed systems and exact D1 query parity

Fifty reviewed central-sector projects expand the public catalog to 518 individual source-backed records. The batch preserves the exact first 320 PAIMANA selections and strengthens mine development, ports and fuel systems, environmental and water utilities, public campuses, generation, transmission, railways, and highways from the same May 2026 official source universe.

370 cumulative PAIMANA records

Every added record retains its official identity, May 2026 status fields, reviewed category rule, source date, cached spatial record, WGS 84 coordinates, precision label, staged ingestion history, and explicit missing-evidence states.

518 individual map features

The catalog contains 394 Major projects or mine assets and 124 Facilities or local schemes. The default non-toll scope contains 429 records; all 89 toll plazas remain available through their explicit opt-in layer, direct links, and intentional search.

Spatial review remains attributable

All 518 positions pass independent state and district containment. Five hundred twelve agree with their declared state scope, the same six earlier NHAI conflicts remain explicit, and the positions resolve across 305 district-code pairs.

D1 compares exact result identities

The staged 518-record import now matches the versioned public read model on ordered project IDs and SHA-256 digests for ten representative catalog, scope, category-state, lifecycle, evidence-tier, awareness, and search queries.

Selection boundary: these 50 records were selected for physical-system scope, reviewable named geography, and spatial-review readiness rather than cost. Previously curated projects, note-named source conflicts, ambiguous multi-state systems, and records without a truthful supported map representation remain outside the batch.

Spatial boundary: representative localities and corridor anchors remain navigation aids, not surveyed sites, alignments, midpoints, rights of way, or project extents. Eight new shared-anchor cases and 31 cumulative collisions retain every original coordinate and an explicit review; no jitter or invented displacement is used.

Read-path boundary: D1 remains a shadow read model. The public map, directory, Project Brief, and evidence views continue to use validated versioned artifacts and remain available if D1 fails. A public D1 cutover still requires database-backed cursor parity, rollback testing, failure isolation, and production latency evidence.

Still incomplete: the 1,987-row PAIMANA source universe still contains 1,617 unselected rows. Many are package-level highway or rail records, ambiguous multi-state systems, or records needing stronger identity and geography review. R2, PMTiles, full-text search, and production-like D1, tile, and concurrency load testing remain future scale work.

Release 64

Twenty-five more reviewed systems and semantic D1 parity

Twenty-five reviewed central-sector projects expand the public catalog to 468 individual source-backed records. The batch preserves the exact first 295 PAIMANA selections and adds aviation, generation, grid, metro, environmental utility, water-supply, public-campus, medical-college, and fuel-network records from the same May 2026 official source universe.

320 cumulative PAIMANA records

Every added record retains its official project identity, May 2026 status fields, reviewed category rule, source date, cached spatial record, WGS 84 coordinates, precision label, and explicit missing-evidence states.

468 individual map features

The catalog contains 344 Major projects or mine assets and 124 Facilities or local schemes. The default non-toll scope contains 379 records; all 89 toll plazas remain available through their explicit opt-in layer, direct links, and intentional search.

Spatial review remains attributable

All 468 positions pass independent state and district containment. Four hundred sixty-two agree with their declared state scope, the same six earlier NHAI conflicts remain explicit, and the positions resolve across 287 district-code pairs.

D1 checks meaning, not only row count

The staged 468-record import now verifies catalog and default-scope totals plus representative category-state, lifecycle, evidence-tier, awareness, and state-facet counts. The public map still reads validated versioned artifacts and remains usable when D1 is unavailable.

Selection boundary: these 25 records were selected for physical-system scope, reviewable named geography, and spatial-review readiness rather than cost. Known duplicate base projects and broad multi-state rows without a truthful map representation remain outside this batch.

Spatial boundary: representative localities and corridor anchors remain navigation aids, not surveyed sites, alignments, midpoints, rights of way, or project extents. Two new shared-anchor cases and 23 cumulative collisions retain every original coordinate and an explicit review; no jitter or invented displacement is used.

Rendered review: the exact production build was reviewed at 320, 390, 820 portrait, 1180 landscape, 1440, and 1920 pixels. The 379-record default directory, individual map features, new AIIMS Bibinagar Project Brief, phone detail sheet, selected-marker framing, and explicit basemap-failure directory remained usable without page-level horizontal overflow or browser console errors.

Scale boundary: D1 remains a shadow read model rather than the source of public facts. Field-level query parity, database-backed cursors, rollback testing, production latency evidence, R2, PMTiles, full-text search, and viewport activation remain future work.

Release 63

Fifty more major systems and a staged D1 parity check

Fifty reviewed central-sector projects expand the public catalog to 443 individual source-backed records. The batch preserves the exact first 245 PAIMANA selections and adds airports, generation and grid systems, metros, urban water and environmental utilities, public campuses and hospitals, pipelines, rail corridors, highways and bridges, and water-resource systems from the same May 2026 official source universe.

295 cumulative PAIMANA records

Every added record retains its official project identity, current May 2026 status fields, reviewed category rule, source date, representative position or facility point, WGS 84 coordinates, precision label, and explicit missing-evidence states.

443 individual map features

The catalog contains 319 Major projects or mine assets and 124 Facilities or local schemes. The default non-toll scope contains 354 records; all 89 toll plazas remain available through their explicit opt-in layer, direct links, and intentional search.

Spatial review remains attributable

All 443 positions pass independent state and district containment. Four hundred thirty-seven agree with their declared state scope, the same six earlier NHAI conflicts remain explicit, and the positions resolve across 276 district-code pairs.

D1 parity is independently observable

A Sites D1 binding and idempotent 443-record migration stage the same project, current-fact, spatial, state-facet, and awareness rows. A separate status endpoint checks the imported count while the public map continues to use validated versioned read artifacts.

Selection boundary: these 50 records were selected for physical-system scope, sector balance, reviewable named geography, and spatial-review readiness rather than cost. Omission does not imply lower importance.

Spatial boundary: representative localities and corridor anchors remain navigation aids, not surveyed sites, alignments, midpoints, rights of way, or project extents. Eight shared anchors retain every original coordinate and an explicit collision review; no jitter or invented displacement is used.

Scale boundary: the public discovery and detail APIs still read validated release artifacts. D1 is a staged semantic-parity path, not yet the source of public project facts; R2, PMTiles, database cursors, production query percentiles, and viewport activation remain future work.

Release 62

Polavaram audit, contract, and funding trail

The 393-record catalog remains unchanged while the Polavaram Irrigation Project gains six official CAG and Ministry of Jal Shakti sources, six structured audit observations, four separately typed money records, three historical construction-contract records, seven exact organization-role rows, and three additional milestones. The record moves from Timeline validated to Contract-linked without changing its representative Polavaram locality point or current PAIMANA facts.

Audit findings stay dated and attributable

The CAG performance audit was tabled on 6 March 2026, covers 2017-18 to 2022-23, and reports project status as of March 2023. Each observation retains the chapter, reviewed pages, amount where applicable, audit reasoning, government reply, CAG response, recommendation, and interpretation boundary.

Three historical agency roles

TRANSSTROY-JSC-EC-UES JV, Navayuga, and Megha Engineering & Infrastructures Limited remain tied to the exact Main Dam, powerhouse, or balance-work roles and dates the CAG publishes. They are not presented as a complete current contractor register.

Money meanings remain separate

The CAG's historical estimates, the Ministry's rounded approved RCE, additional central assistance, cumulative assistance, PAIMANA costs and expenditure, contract values, and audit-calculated consequences remain separately labeled rather than forming an invented cost series.

Current facts and map point are preserved

PAIMANA remains the current source for 86.14% progress, ₹10,151.04 crore original cost, ₹55,548.9 crore revised cost, ₹27,061.89 crore cumulative expenditure, and March 2026 reported completion. No project geometry is inferred.

Audit-time boundary: the CAG audit is not a current status report. Its fieldwork ran from June 2022 to June 2023, its performance scope ends in March 2023, and government replies extend through November 2024.

Finding boundary: the interface says what the CAG reported, calculated, recommended, and answered after the government reply. It does not convert an audit observation into a product-authored allegation of corruption, misconduct, blame, or present failure.

Source-access boundary: the official CAG landing page and documents were reviewed through the public document viewer, but the CAG host did not permit a stable local byte retrieval during this release. The PDFs therefore have page-level review notes but no claimed local SHA-256 fingerprint.

Still incomplete: a complete current contract register, signed contracts and amendments, certified bills and payments, rehabilitation outcomes, current component status, final account, actual or final cost, and authoritative project geometry remain unlinked.

Release 61

Bikaner IV Part A procurement, licence, and monitoring trail

The 393-record catalog remains unchanged while the Bikaner IV renewable-energy transmission Part A scheme gains six fingerprinted official sources, four procurement, agreement, tariff, or licence records, thirteen dated milestones, seven exact organization-role rows, and six CEA-monitored components. The record moves from Timeline validated to Contract-linked without changing its representative Bikaner coordinate.

RFP through final licence

The RECPDCL RFP, Amendment VI, final bid result, CERC tariff-adoption and final licence orders, and CEA May 2026 monitoring report retain direct links, dates, reviewed pages, SHA-256 fingerprints, covered fields, and access limits.

Exact roles without an invented contractor

POWERGRID remains successful bidder and SPV acquirer; POWERGRID Bikaner IV Transmission Limited remains Transmission Service Provider and final licensee. No reviewed source names an EPC contractor or award.

Six money meanings stay separate

₹4,461.05 crore bidding estimate, ₹5,969 crore scheme cost, ₹587.906 crore-per-year selected tariff, ₹657.179 crore-per-year estimated tariff, ₹157.5 crore guarantee, and cumulative expenditure remain differently defined quantities.

Six literal monitoring components

CEA names the 12,000 MVA Bikaner-IV pooling station, four line elements, and a STATCOM with source-literal targets and construction indicators. None becomes synthetic whole-project progress or invented geometry.

Licence boundary: the final inter-State licence does not prove EPC award, construction completion, energisation, commissioning, present operation, tariff recovery, or final cost.

Schedule and entity boundary: Amendment VI's planned dates and CERC's recorded events remain separate. Part A remains distinct from the separately published Siwani Part B project, SPV, cost, tariff, licence, and monitoring row.

Spatial boundary: the unchanged Bikaner marker remains a representative corridor anchor, not the pooling station, a transmission-line route, right of way, surveyed site, or project extent.

Still incomplete: signed agreements, SPV acquisition price, EPC procurement and award, payments, invoices, amendments, disputes, audits, actual completion, operation, actual cost, final cost, authoritative geometry, and status after May 2026 remain unlinked.

Release 60

Bikaner REZ Phase IV Part B procurement, licence, and monitoring trail

The 393-record catalog remains unchanged while the Siwani transmission scheme gains five fingerprinted official sources, four procurement, agreement, tariff, or licence records, twelve dated milestones, seven exact organization-role rows, and five CEA-monitored components. The record moves from Timeline validated to Contract-linked without changing its representative Siwani coordinate.

RFP through final licence

The RECPDCL RFP and Amendment IV, CERC tariff-adoption and final licence orders, and CEA May 2026 monitoring report retain direct links, dates, reviewed pages, SHA-256 fingerprints, covered fields, and access limits.

Exact roles without an invented contractor

POWERGRID remains successful bidder and SPV acquirer; POWERGRID Siwani Transmission Limited remains Transmission Service Provider and final licensee. The licence requires competitive EPC bidding but does not name an EPC contractor or award.

Four money meanings stay separate

₹5,357 crore scheme cost, ₹509.313 crore-per-year selected tariff, ₹564.734 crore-per-year estimated tariff, and ₹139.5 crore guarantee remain differently defined quantities. Cumulative expenditure remains separate again.

Five literal monitoring components

CEA names the 9,000 MVA Siwani substation, three lines, and a STATCOM with source-literal targets and construction indicators. None becomes synthetic whole-project progress or invented geometry.

Licence boundary: the final inter-State licence does not prove EPC award, construction completion, energisation, commissioning, present operation, tariff recovery, or final cost.

Schedule and spatial boundary: November 2026 and June 2027 remain CEA target months, not an inferred breach or blame finding. The unchanged Siwani marker remains a representative corridor anchor, not a substation site, line route, right of way, or project extent.

Still incomplete: signed agreements, SPV acquisition price, EPC procurement and award, payments, invoices, amendments, disputes, audits, actual completion, operation, actual cost, final cost, authoritative geometry, and status after May 2026 remain unlinked.

Release 59

Dhubri-Phulbari bridge approval, procurement, award, and financing trail

The 393-record catalog remains unchanged while the Dhubri-Phulbari Brahmaputra Bridge gains seven reviewed official sources, one construction-award record, nine dated milestones, and four exact organization-role rows. The record moves from Timeline validated to Contract-linked, adds Meghalaya to its official discovery scope, and keeps the existing Dhubri representative corridor point unchanged.

One joined approval-to-award trail

The Cabinet approval, first-cycle annulment notice, re-invited technical evaluation, NHIDCL status register, current project pages, and JICA financing release retain their own dates, fields, fingerprints, and access limits.

L&T has an exact construction role

NHIDCL names Larsen & Toubro Limited, Heavy Civil Infrastructure IC as contractor and publishes ₹3,165.99 crore as Awarded Cost. The product does not relabel JICA, NHIDCL, or MoRTH as the construction contractor.

Five money meanings remain separate

₹4,997.04 crore Total Project Cost, ₹3,548 crore civil-construction cost, ₹3,165.99 crore Awarded Cost, ₹2,837.17 crore cumulative expenditure, and JPY 34,537 million of second-tranche financing are not one revision series.

Cross-state scope without invented geometry

The official record spans Assam and Meghalaya. Search and state filters can find it through either state, while the marker remains the same attributed Dhubri navigation anchor rather than an invented bridge alignment or midpoint.

Progress and freshness boundary: PAIMANA reports 76.01% physical progress by 24 June 2026. NHIDCL's current page separately publishes 76% physical and 74% financial progress but no row-level status date, so those values remain retrieval-dated.

Procurement boundary: the first bidding process was annulled after one responsive bid; the re-invited cycle later reached technical evaluation and award. These facts do not establish fault, corruption, payment, final cost, certified completion, opening, or contractor performance.

Still incomplete: the signed construction contract, amendments, payment certificates, final account, certified completion, opening to traffic, current row date, official alignment geometry, disputes, audits, and authoritative corruption findings remain unlinked.

Release 58

Dholera airport approval, package-award, and status trail

The 393-record catalog remains unchanged while Dholera International Greenfield Airport gains six reviewed official sources, three package contract awards, eight dated milestones, and eight exact organization-role rows. The record moves from Timeline validated to Contract-linked without changing its OpenStreetMap facility representative point.

Approval and current approved cost stay attributable

The 2022 Cabinet approval publishes ₹1,305 crore as the Phase I approved estimate. The MoCA Annual Report 2025-26 publishes ₹1,551 crore as Approved Cost, while PAIMANA labels the same later quantity Revised Cost. The compatible increase is ₹246 crore, or 18.85%.

Three package awards, not one whole-project contractor

AAI names Varaha Infra for operational-area works, Yashnand Engineers and Contractor for the terminal complex, and Saumya Construction for the radar-building package. Each role, reference, award date, scheduled date, and package value remains separate.

Two progress reports remain visibly distinct

PAIMANA reports 84% physical progress in May 2026. PIB reports approximately 80% overall construction on 14 July 2026 and 75% for the terminal building. The product does not infer regression because the source scopes and rounding may differ.

Status targets do not become operation

PIB reports completed components and a September or October 2026 operationalization aim. The airport is not labeled fully complete, licensed, inaugurated, open, or operating without a source that establishes that state.

Money boundary: the ₹636.4454249 crore, ₹333 crore, and ₹18.9880385 crore package awards are not summed as airport cost. PAIMANA's ₹922.78 crore Cumulative Expenditure remains separate from approved cost, payment, actual cost, and final cost.

Schedule and responsibility boundary: past package schedule dates do not prove breach, delay cause, or contractor fault. DIACL is the Cabinet-named implementing company; the three contractors retain package-specific roles.

Still incomplete: signed contracts, amendments, payment records, certified completion, DGCA licensing, opening, present operation, final accounts, disputes, audits, final cost, and official package geometry remain unlinked.

Release 57

Bidar two-cycle procurement, amendment, and tariff trail

The 393-record catalog remains unchanged while the Bidar 2,500 MW solar-zone transmission record gains eight fingerprinted official sources, four procurement or agreement records, fourteen dated milestones, nine exact organization-role rows, and two CEA-monitored components. The record moves from Timeline validated to Contract-linked without changing its representative Bidar coordinate.

Two procurement cycles stay distinct

REC's archive, the initial-cycle Amendment XXI, the re-initiated RFP and Amendment XVII, bidder and result notices, CERC's tariff order, and CEA's May 2026 report retain direct official links, dates, reviewed pages, SHA-256 fingerprints, and source boundaries.

The chronology conflict is not rewritten

CERC says the initial process was annulled in September 2020 due to non-availability of LTA applications, while REC publishes Amendment XXI dated 23 August 2021. The product exposes the conflict and does not invent an exact reconciliation.

Security, tariff, and project cost remain separate

Amendment XVII raises the bid bond and guarantee requirements; POWERGRID's selected offer is ₹236.809 crore per year; CEA and PAIMANA publish ₹1,368 crore as scheme cost. None is silently relabeled as payment, actual cost, or final cost.

Two literal monitoring components

CEA publishes the 479 circuit-kilometre Bidar–Maheshwaram line and 7,000 MVA pooling-station component with source-literal indicators and constraints. The rows load in Timeline without synthetic progress or invented geometry.

Agreement boundary: CERC records the ₹85.90 crore Contract Performance Guarantee, Share Purchase Agreement, SPV acquisition, and tariff adoption subject to licensing. The order is not the signed agreement text, acquisition price, project payment, or proof of present operation.

Schedule and spatial boundary: February 2026 and August 2026 remain source-published target months, not an inferred contractual breach or blame finding. The unchanged Bidar point remains a representative corridor anchor, not the pooling station, line alignment, midpoint, right of way, or project extent.

Still incomplete: signed agreement text, acquisition price, final licence order, complete EPC packages, payments, tariff recovery, disputes, audits, actual cost, final cost, authoritative geometry, and status after May 2026 remain unlinked.

Release 56

Bhadla-Bikaner procurement, tariff, and component trail

The 393-record catalog remains unchanged while the Bhadla-III and Bikaner-III interconnection-strengthening record gains four fingerprinted official sources, three procurement or agreement records, thirteen dated milestones, six exact organization-role rows, and one CEA-monitored line component. The record moves from Timeline validated to Contract-linked without changing its representative Bhadla coordinate.

Four joined official sources

Two PFCCL notices, CERC Order in Petition No. 342/AT/2024, and CEA's May 2026 monitoring report retain direct official links, reviewed pages, evidence and retrieval dates, SHA-256 fingerprints, covered fields, and interpretation boundaries.

Procurement and agreement events, not invented documents

PFCCL names the qualified bidders and L1 result. CERC records the Letter of Intent, ₹30 crore guarantee, Share Purchase Agreement and SPV acquisition events, and tariff adoption. The order is not the signed agreement text or a final licence grant.

The regulator's number conflict stays visible

PFCCL and most CERC bid-result passages publish ₹979.70 million per year; CERC's adoption paragraph publishes ₹979.90 million per year. Both remain separately attributable and neither becomes project cost, payment, actual cost, or final cost.

One literal monitoring component

CEA publishes the 254 circuit-kilometre 765 kV line with 327 locations, 232 foundations, 100 erections, target months, and constraints. The row loads in Timeline and is not converted into synthetic progress or invented geometry.

Money boundary: the ₹901.41 crore CERC project estimate, ₹1,382 crore CEA and PAIMANA scheme cost, ₹97.97 or ₹97.99 crore-per-year charges, and ₹30 crore guarantee remain differently defined quantities. No compatible project-cost revision is inferred.

Schedule and spatial boundary: August 2026 and March 2027 remain published schedule labels, not an inferred contract amendment or blame finding. The unchanged Bhadla point remains a representative corridor anchor, not a pooling station, line alignment, midpoint, right of way, or project extent.

Still incomplete: complete RFP and signed agreement text, acquisition price, amendments, final transmission-licence order, EPC packages, payments, tariff recovery, disputes, audits, actual cost, final cost, authoritative geometry, and status after May 2026 remain unlinked.

Release 55

South Olpad procurement, tariff, and component trail

The 393-record catalog remains unchanged while the Khavda Phase-IV 7 GW Part B transmission record gains three fingerprinted official sources, three procurement or agreement records, nine dated milestones, six exact organization-role rows, and four CEA-monitored components. South Olpad moves from Timeline validated to Contract-linked without changing its representative Olpad coordinate.

Three joined official sources

The PFCCL RFP, CERC Order in Petition No. 493/AT/2024, and CEA May 2026 monitoring report retain direct official links, reviewed pages, evidence and retrieval dates, SHA-256 fingerprints, covered fields, and interpretation boundaries.

Bid and agreement events, not invented documents

CERC records POWERGRID as successful bidder, the Letter of Intent, agreement signing, ₹100 crore Contract Performance Guarantee, and acquisition of the project SPV. The order is a regulatory attestation, not the signed Share Purchase Agreement or Transmission Service Agreement.

Four separate money meanings

The ₹3,605.57 crore CERC estimate, ₹4,766 crore CEA and PAIMANA scheme cost, ₹556.686 crore-per-year adopted tariff, and ₹100 crore guarantee remain separate. No cost revision, payment, actual cost, or final cost is inferred.

Four literal monitoring components

CEA names the South Olpad GIS and three line components with MVA or circuit-kilometre scope, targets, indicators, and constraints. The rows load in Timeline and are not averaged into whole-project progress or represented as invented geometry.

Source difference: CERC paragraph 29 reproduces text calling the selected tariff lower than a numerically smaller levelized tariff, while adjacent paragraphs describe it as 16.33% higher. The inconsistency remains explicit and does not become a project-cost conclusion.

Schedule and spatial boundary: CEA's October 2027 anticipated target is not relabeled as an executed contractual extension or delay finding. The unchanged Olpad point remains a representative corridor anchor, not South Olpad GIS, a line alignment, right of way, or project extent.

Still incomplete: signed agreement text, complete amendments, final transmission-licence order, EPC packages, payments, tariff recovery, disputes, audits, actual cost, final cost, authoritative geometry, and status after May 2026 remain unlinked.

Release 54

Power-grid breadth and Koppal–Gadag component monitoring

Twenty additional Power Grid & Storage systems expand the source-backed national catalog to 393 individual records while preserving the 89-plaza opt-in layer and every earlier evidence trail. Koppal–Gadag also gains a fingerprinted CEA monitoring source with seven named scheme components and source-literal construction indicators.

245 cumulative PAIMANA records

The new breadth batch covers renewable-energy evacuation, pooling stations, interstate corridors, and regional strengthening. It preserves the exact first 225 selections and applies the same source identity, money, schedule, role, precision, provenance, and missing-evidence contract.

393 individual features

The catalog now contains 269 Major projects or mine assets and 124 Facilities or local schemes. The default non-toll scope contains 304 records, while all 89 toll plazas remain discoverable through their explicit opt-in layer, direct links, and intentional search path.

Seven monitored components

CEA's May 2026 report names two substations, three transmission lines, and two augmentation works for Koppal–Gadag. Their circuit-kilometre or MVA scope, target months, indicators, and remarks load in Timeline without becoming synthetic progress, packages, contracts, or whole-project completion.

Containment and source checks refreshed

Three hundred eighty-seven points match their declared state scope, the same six earlier NHAI conflicts remain explicit, and all 393 points resolve to one of 259 district-code pairs. An ambiguous state-versus-anchor candidate was excluded rather than silently relocated.

Compatible scheme fields: CEA publishes ₹4,445 crore as Estimated cost, December 2023 as SPV transfer, December 2025 as Original SCOD, and September 2026 as Anticipated SCOD. These align with the compatible PAIMANA scheme snapshot but are not actual or final cost, payment, expenditure, or proof of completion.

Component boundary: “Stringing”, foundation, tower-erection, land-acquisition, or targeted-charge fields describe the named component in the reviewed CEA row. Release 54 does not turn them into a percent, cause, verdict, contractor performance claim, or whole-scheme state.

Still incomplete: surveyed line geometry, substation coordinates, package tenders, signed contracts, payments, amendments, disputes, audits, actual outturn, final cost, and newer component status remain unlinked.

Release 53

KLI agreement trail and ten-second Project Brief

The Kochi–Lakshadweep Islands submarine OFC record now links two official, page-reviewed agreements and moves from Timeline validated to Contract-linked. The selected-project Overview is also rebuilt as a shorter, type-aware first read while the public catalog remains 373 records, the 284-record default non-toll scope and 89 optional toll plazas remain unchanged, and every source coordinate and precision label is preserved.

Two fingerprinted KLI agreements

The 6 January 2022 implementation agreement and 5 February 2024 tripartite O&M agreement retain direct official links, reviewed page references, SHA-256 fingerprints, exact party roles, dated milestones, and one explicit O&M relationship.

Agreement estimates are not payments

The implementation agreement publishes ₹810.27 crore as total cost to be funded by USOF, excluding taxes and statutory levies. The O&M agreement publishes a tentative ₹51.05 crore initial gross annual estimate, excluding tax. Neither quantity proves a claim, disbursement, vendor payment, annual outturn, actual cost, or final cost.

Overview answers first, evidence follows

The selected workspace now leads with identity, location, source-backed chips, a 50–75 word brief, a type-aware fact grid, one meaningful-change strip when supported, compact milestones, and collapsed organization and evidence summaries. Mine assets omit meaningless development-cost and construction-deadline rows.

Specialist evidence stays lazy

Packages, payments, tenders, fee-agency contracts, revenue records, and other deep evidence are no longer carried in the initial Project Brief response. Timeline, Money, Organizations, Packages, Contracts, and Evidence remain independent, cacheable views with their existing loading and retry boundaries.

Money boundary: the 2022 agreement's ₹810.27 crore funding estimate, DBN's ₹837 crore capital-expenditure field and ₹1,072 crore Total financial implication, the 2024 ₹51.05 crore annual estimate, extra PMC, actual-based claims and DBN's ₹235 crore five-year OPEX use different definitions. They are not silently combined into a revision or payment series.

Spatial and schedule boundary: agreement clauses do not publish a surveyed cable route, landing-station coordinate set, authoritative actual completion date, or revised deadline. Kavaratti remains a representative corridor navigation point, and no delay is calculated by comparing a rollout clause with the later inauguration event.

D1 staging: the idempotent import retains two KLI contract entities, one O&M relationship, two fingerprinted source documents and ten exact project-role rows. The public Site continues to use the validated static read path; D1 and R2 remain staged capability foundations.

Still incomplete: complete claims, advances, disbursements, vendor payments, annual O&M outturns, audit results, reconciliations, recoveries, final adjustments, present network performance, actual cost, final cost, disputes, audit findings and authoritative cable geometry remain unlinked.

Release 52

CANI implementation, amendment, and O&M trail

The Chennai–Andaman and Nicobar Islands submarine OFC record now connects its parent-system evidence to four official, page-reviewed agreement documents. CANI moves from Timeline validated to Contract-linked while the public catalog remains 373 records, the 284-record default non-toll scope remains unchanged, and its representative Port Blair navigation anchor is preserved.

Four agreement records, two money ceilings

The trail separates the 12 July 2018 implementation agreement, 6 November 2019 fund-release amendment, 13 November 2020 tripartite O&M agreement, and 27 January 2026 O&M addendum. The 2018 document publishes ₹929.358 crore as Total CAPEX cost to be funded by USOF; the 2020 document publishes ₹46.84 crore as the annual UT net-OPEX VGF ceiling.

Conditions are not payments

The 2019 amendment requires utilization evidence and proof of vendor payment for later releases. That requirement is not displayed as proof that a payment occurred. Scheduled claims, disbursement, vendor payments, annual O&M outturn, final adjustment, and final cost remain separate and missing unless directly published.

O&M extension stays dated

The 2026 addendum was signed on 27 January 2026, states an effective date of 1 October 2025, and extends the principal O&M agreement through 30 September 2030. It does not publish a new annual ceiling or establish current network availability, maintenance quality, or service performance.

Clause evidence does not upgrade geography

The four PDFs are retained through direct official links, reviewed page references, and SHA-256 fingerprints. They add contract and organization depth without inventing a submarine route, landing-station coordinate, surveyed site, or project extent.

Source difference: the 2018 agreement's ₹929.358 crore USOF CAPEX ceiling, the later DBN page's ₹947.283 crore capital expenditure, and its ₹1,224 crore Total project cost are dated, differently labeled quantities. Release 52 does not silently convert them into one original-versus-revised cost series.

Read model: the staged D1 import now retains two agreement entities, two amendment entities, their two explicit relationships, four fingerprinted source documents, and seven exact CANI organization-role rows. The public Site continues to use the validated static read path; D1 and R2 remain staged capability foundations.

Home and return state: the complete brand block remains the explicit clean-root Home link. Pointer activation or unmodified Enter clears filters, questions, toll opt-in, selection, dossier tab, workspace, result position, and camera; refresh, direct links, shared URLs, modified new-tab activation, and Back or Forward continue to preserve their encoded browser state.

Still incomplete: a complete claims, disbursement, vendor-payment, annual O&M outturn, reconciliation, recovery, or final-adjustment ledger is not linked. Actual or final project cost, current operating performance, payment audit, dispute records, audit findings, and authoritative cable geometry remain missing.

Release 51

Digital Bharat Nidhi submarine-fibre systems

Digital & Telecom is now an active evidence-backed category. Two major physical-network records add the Chennai–Andaman and Nicobar Islands submarine OFC system and the Kochi–Lakshadweep Islands submarine OFC system, bringing the public catalog to 373 individual records: 249 Major projects or mine assets and 124 optional Facilities or local schemes.

Two official parent networks

Digital Bharat Nidhi, Department of Telecommunications, and PIB sources establish named scope, approval, commissioning or completion statements, reported cost definitions, exact organization roles, and inauguration events.

No invented cable route

CANI uses Port Blair and KLI uses Kavaratti only as representative corridor navigation anchors. Both retain cached OSM locality provenance and explicitly reject landing-station, midpoint, surveyed-site, and marine-route interpretations.

Money definitions stay exact

CANI keeps ₹1,224 crore as Total project cost. KLI keeps ₹1,072 crore as Total financial implication excluding taxes, with the later “plus taxes” wording preserved as a source difference. Neither becomes final cost or payment.

Lifecycle events stay separate

CANI's 10 August 2020 and KLI's 3 January 2024 inaugurations are sourced events, not substitutes for exact construction completion, revised deadline, current operation, or service performance.

Default discovery: a fresh browse view now shows 284 non-toll records. The same 89 toll plazas remain in the 373-record catalog and appear only through the explicit Toll plazas layer.

Spatial review: independent state and district containment covers all 373 points. Three hundred sixty-seven match the declared state scope, the same six NHAI conflicts remain explicit, and every point resolves to one of 251 district-code pairs without exporting boundary geometry.

Still incomplete: no reviewed authoritative route LineString or landing-station coordinate register is published. Clause-level agreements, amendments, payments, disputes, actual completion costs, final costs, and current network availability remain future depth work.

Release 50

Tech Atlas basemap parity, 16 infrastructure systems, and sourced inauguration

Infra now uses the complete OpenFreeMap Positron style instead of deleting most provider labels and restyling the map through a warm India wash. Roads, railways, airports, waterways, land cover, buildings, cities, towns, villages, and local labels disclose progressively with zoom while the reviewed India outline, state boundaries, all 371 individual records, and project evidence remain separate and preserved. Only country-label layers are narrowed to India so large neighboring-country names do not compete with the map's subject.

Native Positron context restored

The provider's palette and zoom thresholds now match the Tech Atlas foundation materially more closely. Official India overlays remain above the orientation basemap, and native project layers remain above both.

16-category physical taxonomy

A deterministic migration separates generation, grids and storage, fuel systems, water resources, water supply, environmental utilities, ports, and inland logistics using reviewed sector and source-type rules. Fifteen categories have current records; Digital & Telecom remains dormant until an authoritative record passes review.

Inaugurated is not completed

Kanpur Metro is the first explicitly sourced example. UPMRC records the 30 May 2025 Motijheel to Kanpur Central inauguration and 14 operational stations while also saying construction on remaining sections was ongoing.

Lifecycle and relationships prepared

The discovery API, URL, result chip, preview, Project Brief, Timeline, current-facts model, D1 import, and indexed lifecycle table carry the sourced event. The existing source-attributed entity-relationship foundation remains ready for future network links without synthesizing routes.

Evidence boundary: inauguration is stored with its date, scope, source, reporting cutoff, and named inaugurating officeholder only where the official report publishes them. It does not imply full-project construction completion, commissioning, opening, 100% progress, or current operation.

Default discovery: a fresh browse view now shows 282 non-toll records. All 89 reviewed toll-plaza records remain in the unchanged 371-record catalog and appear only when the accessible Toll plazas layer is enabled. The toggle composes with search, questions, categories, lifecycle, geography, evidence filters, results, markers, and shared URLs; a named toll search offers a direct enable-layer action, and direct toll-project URLs still open.

Home behavior: the complete India Infra Map brand lockup is a semantic Home link. Normal activation performs a clean-root navigation that clears discovery, dossier, workspace, result-position, and camera state; modified clicks retain standard open-in-new-tab behavior, while refresh, Back and Forward, direct project links, and shared stateful URLs keep their encoded restoration behavior.

Rendered reference review: an anonymous public browser check on 16 July 2026 reached Tech Atlas with the title “Tech Atlas | 581 reviewed Bay Area tech companies” and no login gate. Initial, wheel, pan, zoom, reset, hover, focus, selection, right-workspace, phone, tablet, laptop, wide-screen, and blocked-basemap states were compared with Infra. The provider palette, disclosure hierarchy, full-bleed composition, and restrained 410-pixel desktop workspace align; Infra deliberately keeps smaller precision-aware native features, India overlays, URL state, stronger keyboard preview, and an explicit map-failure directory instead of copying Tech Atlas's 581 DOM logo markers or Bay Area semantics.

Coverage boundary: Release 50 preserves all 371 records and adds no weak breadth record merely to populate a new category. Digital & Telecom has an icon and schema identity but is not offered as an active filter until reviewed records exist. Space and sensitive strategic infrastructure remain deferred.

Release 49

Two hundred twenty-five reviewed PAIMANA projects

Twenty-five additional source-backed Major projects bring the public catalog to 371 individual records: 247 Major projects or mine assets and 124 optional Facilities or local schemes. The exact first 200 PAIMANA selections remain unchanged, and the ninth batch broadens public-system, institution, industrial, energy-network, rail, metro, highway, hydropower, and mining-development coverage.

225 cumulative PAIMANA records

The reviewed breadth lane still derives from the same 1,987-row May 2026 PAIMANA source universe across 34 state or union-territory scopes and 20 official sectors. Selection uses published scope, geography, capacity, corridor role, public function, regional balance, and spatial-review readiness, not cost ranking.

371 individual features

Every active record keeps its reviewed coordinate and precision. Agra sewerage and Agra Metro explicitly share one city navigation anchor, bringing the cumulative total to nine reviewed collision groups with no clustering, jitter, random displacement, or invented exactness.

Representative remains representative

The new campus, corridor, system, locality, and mine-development anchors are navigation evidence, not project geometry. AIIMS Delhi uses a reviewed campus subfacility; IISER Berhampur uses broad Brahmapur context; neither point is presented as a construction footprint.

Independent containment refreshed

State containment returns 365 matches and preserves the same six explicit NHAI conflicts. District containment resolves every point across 250 district-code pairs without downloading or republishing boundary geometry.

Source freshness: the MoSPI release calendar schedules the June 2026 Flash Report for 25 July 2026, so the May 2026 report remains the newest published national PAIMANA breadth source reviewed for this 16 July release.

Still incomplete: these breadth records do not yet provide complete tender, award, signed contract, contractor, payment, amendment, dispute, audit, final-cost, or official project-geometry trails. The 225-record lane is a reviewed sample, not full PAIMANA or national coverage.

Release 48

Smaller project medallions and progressive India context

The national map now gives every published record a compact circular category medallion while restoring useful Positron road, transport, water, land-cover, built-environment, and place context progressively by zoom. All 346 records, source coordinates, precision meanings, filters, lenses, URLs, Project Briefs, and evidence trails remain unchanged.

15 to 18 pixel everyday marks

Facilities start around 14.5 pixels and Major records around 17 pixels at national zoom, with modest zoom interpolation. Selected records use a 24-pixel category-filled state and a neutral halo instead of enlarging every passive marker.

Precision becomes a secondary ring

Solid, double, dotted, tailed, mine-representative, and unresolved treatments remain visible, but no longer turn every record into a large square, diamond, or corridor badge. Direct text and evidence remain authoritative.

Provider context returns by zoom

National view keeps official India and state context calm. Regional and closer views progressively reveal roads, rail orientation, airports, waterways, towns, villages, neighbourhoods, and built areas without restoring low-value country-label noise.

Project-first resilience retained

Real project points and the official India outline remain independent of optional provider glyphs, sprites, and context layers. Search, results, selection, Project Briefs, specialist evidence, and map-failure access continue to work separately.

Orientation boundary: OpenStreetMap and OpenMapTiles roads, airports, stations, waterways, buildings, and place labels help people orient themselves. They do not establish a monitored project, project geometry, construction state, cost, deadline, contractor, progress, or evidence tier.

Collision boundary: every active record remains an individual coordinate-locked feature without clustering, count pills, jitter, or invented displacement. Zoom remains the current separation path for dense locations; deterministic cycling or click expansion is still future work.

Release 47

Chennai Metro Phase II contract trail

Chennai Metro Phase II now connects its April 2026 PAIMANA progress, cost, and schedule snapshot to CMRL's current project status, archived and current awarded-tender registers, and two signed-contract releases. The record moves from Basic official record to Contract-linked while preserving all 346 published records and the existing Chennai locality representative point.

58 of 60 packages reported awarded

CMRL's page updated 24 March 2026 reports all 19 civil and five track packages awarded, with 34 of 36 systems packages awarded and two under finalisation. Those aggregate counts remain separate from the 28 evidence-linked rows reviewed here.

28 bounded package rows

The dossier links civil, station, tunnel, track, systems, depot, and station-access rows with exact package references and sourced organization roles. It does not describe this slice as the complete 60-package register.

Amount definitions stay separate

Rows include differing provisional-sum, GST, customs, tax, and duty bases. No package-row sum is presented as total awarded value, project cost, expenditure, payment, actual cost, or final cost.

D1 evidence entities prepared

The staged import retains five CMRL sources, 28 packages, two signed-contract records, and scope-specific organization roles. The public Site remains on the validated static read path; D1 and R2 are still unbound.

Source difference: CMRL's archive prints ₹91,85,06,227.23 and ₹89,85,06,227.23 for the same ASA07 tender reference, a ₹2 crore difference. No reviewed source labels either value a revision or superseding amount, so both remain visible and unresolved.

Still incomplete: the complete 60-row package register, consistent package values, payments, amendments, variations, claims, disputes, audits, final package values, current or final project cost, and official corridor geometry remain unlinked. A signed agreement does not prove present-day performance or completion.

Release 46

Mumbai–Ahmedabad High-Speed Rail contract trail

The 508 km Mumbai–Ahmedabad High Speed Rail record now connects its April 2026 PAIMANA progress, cost, and schedule snapshot to NHSRCL's official package structure, aggregate civil-award release, agreement records, and a bounded selection of core awarded-tender rows. The project moves from Basic official record to Contract-linked while keeping all 346 records, the existing representative corridor point, and every earlier evidence trail unchanged.

17 core package rows

The dossier links all 11 civil package identities plus two steel-bridge, two track, one depot, and one training-institute row. NHSRCL's 2023 release says all 11 civil packages were awarded, but package-specific firms, dates, and values appear only where the reviewed official links support them.

Native currencies stay separate

C4, C6, P4X, P4Y, and T3 retain their published INR, JPY, and USD components without conversion or summation. Pure INR values are not rolled into a whole-project award total, cost, expenditure, payment, actual cost, or final cost.

One duplicate remains unresolved

The NHSRCL awarded register contains two D2 rows for the same named consortium with values differing by ₹591.755299576 crore. Neither row is relabeled as a revision, amendment, variation, overrun, or final amount.

D1 evidence entities prepared

The staged import retains eight NHSRCL sources, 17 packages, three project-level contract records, and 16 exact organization-role rows. The public Site remains on the validated static read path; D1 and R2 are still unbound.

Source evolution: NHSRCL's package-structure page is marked 13 August 2019. Later dated award and agreement sources supersede that snapshot's procurement state only for the facts they publish. Bidder and technical-bid pages are not treated as award proof.

Still incomplete: package-specific award dates, agreements, organizations, and values remain incomplete across the reviewed slice. A complete payment, amendment, variation, dispute, audit, and final-cost trail is not linked, and the map position remains a representative corridor point rather than official alignment geometry, package extent, station, or work site.

Release 45

Mumbai Metro Line 3 contract trail

Mumbai Metro Line 3 now connects its PAIMANA progress, cost, expenditure, and schedule snapshot to MMRCL's official package-status, funding, consultant, and operations work-order pages. The record moves from Timeline validated to Contract-linked while keeping its representative corridor point and every earlier catalog record unchanged.

22 rows, 18 main packages

MMRCL states that the project has 18 main packages. Lettered subpackages and lots produce 22 displayed rows; 19 show an award or Letter of Acceptance state, and the General Consultant row remains a separate exact role.

Partial package money stays partial

Thirteen package rows publish amounts totaling ₹19,640.03 crore. Nine rows do not. The sum is never presented as total awarded value, project cost, expenditure, payment, actual cost, or final cost.

Six work orders, exact roles

Six operations-related work orders retain their named parties, issue dates, tenures, amounts, and retrieval-dated status boundary. Package contractors, the General Consultant, and operations parties are not relabeled as one whole-project contractor.

D1 evidence entities prepared

The staged import now carries four MMRCL source documents, 22 packages, six contracts, and 32 scope-specific organization-role rows. The public Site remains on the validated static read path; D1 and R2 are still unbound.

Funding boundary: MMRCL publishes ₹23,136 crore as Total Project Completion Cost, while its eight displayed funding components sum to ₹23,137 crore and 100%. The ₹1 crore displayed difference remains visible. This funding plan is not substituted for PAIMANA's ₹37,276 crore Revised Cost or ₹33,648.26 crore Cumulative Expenditure.

Still incomplete: most package award dates, nine package amounts, package payment series, signed contract files, amendments, variations, disputes, audits, current operations performance, and final package or project costs remain unlinked. The work-order register does not prove present-day service status or full-project completion.

Release 44

Six evidence questions with exact reasons

The browse workspace can now answer six deterministic, shareable public-awareness questions: airports in progress, explicit high-speed rail, past reported deadlines, completion dates moved by at least ten years, compatible revised costs at least twice the original, and records carrying an explicit freshness warning. Every result states why it matched, while the question summary exposes the scope, required fields, denominator, missing-data count, and catalog date.

346 records preserved

The questions are materialized from the same reviewed current facts. They add no project, coordinate, organization role, cost, date, or lifecycle claim and do not change the 222 Major or mine-asset and 124 Facility or local-scheme split.

Reporting cutoffs stay record-specific

Deadline comparisons now use each record's own status snapshot. The 200 PAIMANA breadth records use 24 June 2026; the earlier curated project snapshot uses 30 April 2026. Records without the required fields remain in the denominator as missing rather than being inferred.

Questions remain map questions

Choosing a question keeps every matching record as an individual coordinate-locked feature and switches to the most useful existing lens. The complete question and current filters are retained in the shareable URL.

Database parity prepared

Six awareness states per record now import idempotently into the staged D1 schema with a query index. The public Site still uses the validated static read path; D1 and R2 remain unbound.

Current answers: 17 airports report progress between 1% and 99%; one reviewed record is explicitly high-speed rail; 22 projects had passed their reported deadline in the same status snapshot; five completion dates moved by at least ten years; 16 compatible revised costs are at least twice their original; and 29 records carry an explicit freshness warning.

Measured local check: an unthrottled cache-disabled 390 by 844 run showed the source-backed overview at 24.5 ms, browse controls at 63.0 ms, all 346 native project features at 160.7 ms, orientation geography at 226.9 ms, FCP and LCP at 56 ms, zero layout shift, no long task, and about 33.3 MB used JS heap. The comparable Release 43 run recorded 18.6, 74.8, 119.8, and 194.3 ms, FCP and LCP at 72 ms, and about 61.3 MB. A 1.4-second map-drag sample reported 60.1 fps, 17.7 ms p95 frame time, and no frame over 50 ms. Twenty sequential warm local question requests measured 1.3 ms p95. These are controlled local observations, not production percentiles; the later marker and geography times remain within the interaction session but are modestly slower than the earlier single run.

Interpretation boundary: these are source-bounded comparisons, not findings about cause, fault, delay responsibility, corruption, waste, success, current operation, or present-day status. A record without a freshness warning is not certified current or complete.

Release 43

Two hundred reviewed PAIMANA projects

Twenty-five more source-backed Major projects bring the public catalog to 346 individual records: 222 Major projects or mine assets and 124 optional Facilities or local schemes. The first 175 PAIMANA records remain in their exact published order. The new batch adds airports, metros, rail, a Brahmaputra bridge, highways, hydro and power systems, energy pipelines, major water systems, a national public-university campus phase, and coal development without changing the accepted map, evidence, search, Project Brief, URL, accessibility, or fallback behavior.

200 cumulative PAIMANA records

The reviewed lane still derives from the same 1,987-row May 2026 PAIMANA source universe across 34 state or union-territory scopes and 20 official sectors. Selection follows published system scope, geography, capacity, network role, and public function, not cost ranking.

346 individual map features

Every active record keeps its reviewed coordinate and precision. Three new shared navigation anchors are documented explicitly, bringing the cumulative total to eight collision groups with no clustering, jitter, random displacement, or invented exactness.

Official range stays approximate

Heo and Kiru retain direct official point meanings. Tirap uses a documented representative point derived from an official project-area coordinate range, not a source-published point, mine boundary, lease centroid, extraction footprint, or operating-state claim.

346 points rechecked

State containment returns 340 matches and the same six explicit NHAI conflicts. District containment resolves every point across 237 district-code pairs without exporting boundary geometry.

Measured local check: under the same cache-disabled 1.6 Mbps, 150 ms latency, 4-times CPU, 390 by 844 profile, the 346-record overview appeared at 3.40 seconds, browse controls at 9.51 seconds, all native project features at 12.16 seconds, and orientation geography at 15.34 seconds, with zero layout shift and no long task. The Release 42 321-record values were 3.40, 9.12, 11.95, and 15.14 seconds. An unthrottled cache-disabled run showed the overview at 18.6 ms, browse controls at 74.8 ms, all 346 project features at 119.8 ms, FCP and LCP at 72 ms, zero layout shift, no long task, and about 61.3 MB used JS heap. A 1.2-second map-drag sample reported 61.2 fps, 17.5 ms p95 frame time, and no frame over 50 ms. The constrained Tirap Project Brief became visible in 3.06 seconds; its brief API request took 178 ms. These are controlled local observations, not production percentiles.

Still incomplete: these PAIMANA breadth records do not yet provide complete tender, award, signed contract, contractor, payment, audit, dispute, final-cost, or project-geometry trails. The 200-record lane is a reviewed sample, not full PAIMANA or national coverage.

Release 42

One hundred seventy-five reviewed PAIMANA projects

Twenty-five more source-backed Major projects bring the public catalog to 321 individual records: 197 Major projects or mine assets and 124 optional Facilities or local schemes. The first 150 PAIMANA records remain in their exact published order. The new batch adds airports, metros, rail, Ganga bridges, highways, hydro and power systems, coal and mining development, and major irrigation systems without changing the accepted map, evidence, search, Project Brief, URL, accessibility, or fallback behavior.

175 cumulative PAIMANA records

The reviewed lane still derives from the same 1,987-row May 2026 PAIMANA source universe across 34 state or union-territory scopes and 20 official sectors. Selection follows published system scope, geography, capacity, network role, and public function, not cost ranking.

321 individual map features

Every active record keeps its reviewed coordinate and precision. Three new shared navigation anchors are documented explicitly, bringing the cumulative total to five collision groups with no clustering, jitter, random displacement, or invented exactness.

Supporting context stays bounded

Four official publications support named context for Tato-II, Pugal Solar Park, Subarnarekha irrigation, and the Indiramma canal. They do not silently import lifecycle, procurement, financial, benefit, or geometry claims.

321 points rechecked

State containment returns 315 matches and the same six explicit NHAI conflicts. District containment resolves every point across 228 district-code pairs without exporting boundary geometry.

Measured local check: under the same cache-disabled 1.6 Mbps, 150 ms latency, 4-times CPU, 390 by 844 profile, the 321-record overview appeared at 3.40 seconds, browse controls at 9.12 seconds, all native project features at 11.95 seconds, and orientation geography at 15.14 seconds, with no long task. The Release 41 296-record results were 3.73, 8.66, 11.70, and 14.88 seconds respectively. An unthrottled local run showed the overview at 46.5 ms, all 321 project features at 209 ms, FCP and LCP at 164 ms, CLS 0.1, and one 74 ms startup long task; an 820-pixel selected-view drag sample reported 60 fps, 18 ms p95 frame time, and no frame over 50 ms. These are controlled local observations, not production percentiles.

Still incomplete: these PAIMANA breadth records do not yet provide complete tender, award, signed contract, contractor, payment, audit, dispute, final-cost, or project-geometry trails. The 175-record lane is a reviewed sample, not full PAIMANA or national coverage.

Release 41

Real project geography appears before the interactive map is ready

The catalog, source coordinates, spatial precision, evidence, Project Briefs, filters, URLs, and individual MapLibre features remain unchanged. Startup now leads with a build-generated national overview containing all 296 published records at their reviewed coordinates while the interactive renderer and directory finish loading.

296 real loading features

The overview uses the reviewed India outline and state boundaries, one feature per published record, category color, precision shape, and the existing Major or Facility hierarchy. It is explicitly non-interactive and never substitutes for the evidence map.

Pinned renderer runtime

The build copies and validates the exact MapLibre GL JS 5.24.0 distribution, including version, byte count, BSD-3-Clause license, and SHA-256 hash. A stable versioned path lets the browser reuse the preload instead of waiting for a second application chunk.

Truth and fallback stay separate

Native project layers can initialize after style prerequisites instead of waiting for unrelated provider glyphs. The curated Indian state and city context still installs from reviewed assets, and a basemap failure still leaves the complete directory and evidence routes usable.

Less startup contention

System typography removes eleven font requests from the first path. The spatial index and MapLibre runtime preload at low priority while the national overview receives first visual priority.

Measured local change: under the same cache-disabled 1.6 Mbps, 150 ms latency, 4-times CPU, 390 by 844 profile, the truthful overview appeared at 3.73 seconds and all 296 native project features at 11.70 seconds, down from 22.44 seconds. Browse controls improved from 9.40 to 8.66 seconds, orientation geography from 25.45 to 14.88 seconds, and the run recorded no long task. An unthrottled 1,440 by 900 drag and wheel sample reported 60.7 fps with no frame over 50 ms. These are controlled local observations, not production percentiles.

Still incomplete: the constrained native-feature time remains above the aspirational 3-second mobile budget, and the pinned renderer is still the largest startup asset. Production p75 evidence, D1 reads, R2 or PMTiles delivery, viewport activation for much larger catalogs, and the next evidence expansion remain staged.

Release 40

One hundred fifty reviewed PAIMANA projects

Twenty-five more source-backed Major projects bring the public catalog to 296 individual records: 172 Major projects or mine assets and 124 optional Facilities or local schemes. The first 125 PAIMANA records remain in their exact published order. The sixth batch adds coverage across 11 official sectors and 14 state or union-territory scopes, with particular attention to Northeast, Himalayan, Punjab, energy, minerals, water, bridge, road, rail, and public-institution systems.

150 cumulative PAIMANA records

The reviewed lane still derives from the same 1,987-row May 2026 PAIMANA source universe. Selection is not a cost ranking and preserves explicit gaps in contracts, payments, audits, disputes, and geometry.

Two more official hydro references

NHPC and SJVN publications provide coordinates for Rangit IV and the Dhaulasidh dam location. Both are converted transparently to WGS 84 and retain their exact published role rather than becoming invented project extents.

True collisions stay truthful

Two new projects share previously reviewed Numaligarh and Kirandul navigation anchors. All four records remain individual features at their original coordinates, with no clustering, jitter, or invented displacement.

296 points rechecked

State containment returns 290 matches and the same six explicit NHAI conflicts. District containment resolves every point across 218 district-code pairs without exporting boundary geometry.

Performance check: a cached local production run showed all 296 markers in 386.1 ms and a 61.2 fps drag sample with no frame over 50 ms. A cache-disabled 1.6 Mbps and 4-times CPU mobile profile remained over budget, with the spatial index at 9.54 seconds and first markers at 22.46 seconds. These are local observations, not production percentiles; the constrained startup path remains a stated scale limit.

Still incomplete: these PAIMANA breadth records do not yet provide complete tender, award, signed contract, contractor, payment, audit, dispute, final-cost, or project-geometry trails. The 150-record lane is a reviewed sample, not full PAIMANA or national coverage.

Release 39

One hundred twenty-five reviewed PAIMANA projects

Twenty-five more source-backed Major projects bring the public catalog to 271 individual records: 147 Major projects or mine assets and 124 optional Facilities or local schemes. The first 100 PAIMANA records remain in their exact published order, while the accepted map, evidence, search, Project Brief, specialist, URL, accessibility, and fallback behavior remains intact.

125 cumulative PAIMANA records

The fifth deterministic batch spans 11 official sectors and 20 published source scopes. Selection follows official system scale, geography, capacity, corridor role, and public function, not cost alone.

One official project reference

An SJVN document provides the Sunni Dam project-location coordinate. It is converted transparently to WGS 84 but is not presented as a dam axis, powerhouse, reservoir boundary, parcel, or complete extent.

Spatial limits stay visible

The other 124 PAIMANA records retain source-attributed representative features. Rail endpoints, towns, stations, airports, and system localities remain navigation evidence rather than invented project geometry.

271 points rechecked

State containment returns 265 matches and the same six explicit NHAI conflicts. District containment resolves every point across 205 district-code pairs without exporting boundary geometry.

Still incomplete: these PAIMANA breadth records do not yet provide complete tender, award, signed contract, contractor, payment, audit, dispute, final-cost, or project-geometry trails. The 125-record lane is a reviewed sample, not full PAIMANA or national coverage.

Release 38

The PAIMANA Major lane reaches one hundred reviewed projects

Twenty-five more source-backed Major projects bring the public catalog to 246 individual records: 122 Major projects or mine assets and 124 optional Facilities or local schemes. Content-addressed read models and release-versioned API requests ensure returning browsers retrieve one matching catalog instead of combining old and new cached artifacts. The accepted map, evidence, search, Project Brief, specialist, URL, accessibility, and fallback behavior remains intact.

100 cumulative PAIMANA records

The same 1,987-row official candidate universe now supports 34 state or union-territory scopes and 20 official sectors. The first 75 selections remain byte-order stable.

Seven system families expanded

The new batch adds four airport systems, five metro systems, four energy pipelines or terminals, five water-resource systems, five rail corridors, one port project, and one national scientific institution.

Navigation points stay approximate

Airport features, city anchors, rail endpoints, pipeline endpoints, water-system localities, and port-area features remain separately sourced representatives. None is promoted to project geometry.

246 points rechecked

State containment returns 240 matches and the same six explicit NHAI conflicts. District containment resolves every point across 194 district-code pairs without exporting boundary geometry.

Still incomplete: these PAIMANA breadth records do not yet provide complete tender, award, signed contract, contractor, payment, audit, dispute, final-cost, or official project-geometry trails. The hundred-record lane is a reviewed sample, not full PAIMANA or national coverage.

Release 37

Seventy-five PAIMANA projects widen the Major layer

Twenty-five source-backed Major projects extend the reviewed PAIMANA lane without changing its first 50 records. The public catalog now contains 221 individual records: 97 Major projects or mine assets and 124 optional Facilities or local schemes.

75 cumulative PAIMANA records

The same 1,987-row official candidate universe now supports 34 state or union-territory scopes and 19 official sectors. Puducherry joins the lane for the first time.

Mining meaning stays exact

Seven copper, bauxite, iron-ore, processing, and coal records are mining development projects. They are not silently promoted to mine assets or current operating-state claims.

Representative means representative

Every PAIMANA point retains its cached source entity, query, coordinates, retrieval date, transformation, and limitation. Official Talabira and AIIMS Madurai context narrows interpretation without turning a district or locality anchor into a project site.

221 points rechecked

State containment returns 215 matches and the same six explicit NHAI conflicts. District containment resolves every point across 181 district-code pairs without exporting boundary geometry.

Still incomplete: PAIMANA breadth records do not yet provide complete tender, award, signed contract, contractor, payment, audit, dispute, or official project-geometry trails. These gaps remain visible, and the existing deep-dossier lane continues separately.

Release 36

The directory now loads one evidence-aware result page at a time

All 196 reviewed records, individual map features, source coordinates, precision, evidence, Project Briefs, filters, URLs, and public access remain unchanged. The healthy browse path no longer downloads the complete 316,598-byte current-facts artifact before the directory becomes useful.

24-row cursor pages

A stable versioned API returns deterministic pages, exact matching and catalog counts, filter facets, missing-data counts, catalog-generation date, and a concise match reason for each result.

All matches stay on the map

The current 196-record response keeps the complete matching ID set, so filtering a page never hides an eligible project merely because its result row has not been loaded yet. No clustering, sampling, or coordinate movement is introduced.

94% smaller first browse JSON

The validated first response is 19,100 uncompressed JSON bytes, down from the 316,598-byte full fact artifact. A local rendered HTTP run encoded that response to about 5.7 KB. These are payload observations, not field percentiles.

Static fallback remains

If the discovery API fails, the browser retrieves the same validated current-facts artifact and restores local search, filters, counts, results, and map activation instead of losing the directory.

Still incomplete: the API reads the versioned release artifact rather than D1, and returning all matching IDs is appropriate for 196 records but not a million-record viewport. Database cursors, full-text search, viewport activation, PMTiles, immutable hosting caches, production concurrency evidence, and new project coverage remain staged.

Release 35

Official map context now arrives in a compact verified package

All 196 reviewed records, source coordinates, precision, evidence, Project Briefs, interaction, and public access remain unchanged. The reviewed India outline, state boundaries, and state labels now hydrate from three content-addressed gzip assets with independent raw-source fallbacks.

69% less geography transfer

The three reviewed GeoJSON sources total 1,604,961 raw bytes. Their deterministic compressed package totals 504,470 bytes without changing a geometry, label, coordinate, or provenance record.

Equivalence is validated

The release gate checks source hashes, raw and compressed byte counts, feature counts, decompression, deep GeoJSON equality, and the existing line, vertex, label, CRS, derivation, and provenance rules.

Fallback stays truthful

A missing manifest, unavailable browser stream, failed compressed request, or decompression error falls back to the reviewed raw asset. If both paths fail, map context reports its own unavailable state without removing search, records, or evidence.

Progressive orientation

The map no longer fetches the raw India outline twice. Curated national city context arrives with geography, while denser Indian town and village labels install only at their supported close zoom after the gesture settles.

Still incomplete: this is a compact release artifact, not PMTiles or a production D1 or R2 read path. The 196-record current-fact index still loads in the browser, Evidence remains the largest specialist response, and this release adds no new project coverage.

Release 34

Specialist evidence now loads one section at a time

All 196 reviewed records, evidence semantics, coordinates, map interaction, Project Briefs, and public access remain unchanged. Timeline, Money, Organizations, Packages, Contracts, and Evidence now have independently cached specialist sections.

Six section responses

The stable selected-record API gives every specialist view its own versioned cache identity while keeping the full investigation response for compatibility.

Intent-sized retrieval

A reader opening Packages no longer downloads unrelated dispute, money, or evidence prose. Returning to an already loaded section uses the local cache.

Failure stays local

A failed section can be retried without removing Overview, the map, or another specialist section that already loaded successfully.

Truth contract preserved

Section patches are generated from the same reviewed record and validated without changing identity, coordinates, precision, roles, values, or source records.

Still incomplete: Evidence remains the largest specialist response because nested source fields are restored across the dossier. The current-fact index and raw geography remain larger browser payloads, D1 and R2 are still unbound, and this release adds no new project coverage.

Release 33

The Project Brief now arrives before specialist evidence

All 196 reviewed records, evidence ledgers, coordinates, precision, map layers, discovery state, and public access remain unchanged. Selecting a record now retrieves a compact Project Brief first. Timeline, Money, Organizations, Packages, Contracts, and Evidence are retrieved only after a reader opens a specialist tab.

Brief-first response

The versioned API now separates brief and investigation views with distinct cache identities. The brief preserves the complete Overview, source identities, freshness, spatial precision, and section counts while omitting specialist explanatory prose until it is requested.

37.8% smaller deep first read

In the final local production build, the Tundla Project Brief response is 11,312 bytes and the full investigation response is 18,181 bytes. This is a payload measurement for one deep dossier, not a field performance percentile.

Failure stays bounded

Loading, unavailable, retry, and return-to-Overview states are explicit. A specialist request can fail without removing the map, selected record identity, or Project Brief.

Accessible investigation flow

Tab focus, Enter and Space activation, arrow navigation, Home, End, phone sheets, tablet workspaces, and desktop panels preserve the selected record and map context.

Still incomplete: the first specialist action currently retrieves one cached investigation bundle, so later specialist tabs do not make another request but are not yet independently partitioned. The current-fact index and raw geography remain larger browser payloads, D1 and R2 are still unbound, and this release adds no new project coverage.

Release 32

The map now reads like an infrastructure atlas before a reader opens a record

The 196 reviewed records, evidence ledgers, coordinates, precision, native MapLibre delivery, selected-record API, search, filters, URLs, Project Briefs, and public access are unchanged. The visual system now follows the approved pale-water, warm-land, compact-command, multicolor-medallion, and answer-first dossier direction without importing any illustrative value from the art reference.

14 infrastructure medallions

Professional pictograms and restrained category rings now identify airports, rail, metro, roads, water, energy, mining, industry, logistics, and other reviewed types. Airport uses coral and mining uses dark earth; category no longer collapses into an electric-blue default.

Meaning stays separated

The center identifies category, the backplate identifies spatial precision, an optional outer ring carries the selected metric, and a neutral halo carries selection. A locality, corridor, official facility, mine representative, and unresolved point remain visibly different.

Command-map composition

A compact infrastructure-and-map identity, prominent search, working discovery shortcuts, pale blue water, warm land, muted surroundings, and a collapsible map key keep India dominant while the single right workspace remains adaptive.

Evidence first read preserved

The Project Brief reuses the category medallion and keeps the evidence-checked TL;DR, exact money and schedule meanings, organization roles, procurement gaps, freshness, spatial precision, and paths to specialist tabs.

Still incomplete: the visual hierarchy does not solve current geographic density at a few national-scale hotspots, create missing line or area geometry, activate D1 or R2, split specialist-tab payloads, or add a submission workflow. All 196 active records remain individual by design, so overlap is resolved through zoom and filtering rather than count clusters or coordinate movement.

Release 31

Real project points arrive first, and the catalog no longer ships inside the app bundle

The 196 Release 30 records, evidence ledgers, coordinates, precision, categories, filters, Project Briefs, and public access remain unchanged. A compact spatial index now hydrates before current discovery facts, while selecting a record retrieves that one dossier through a stable versioned API path.

196 native map features

An independent MapLibre point source paints every active record before the glyph-heavy precision and category layers settle. Feature state handles hover and selection without DOM-marker rebuilds, clustering, count pills, jitter, or random sampling.

Bundle split

The main map component falls from about 1.65 MB raw to about 172 KB raw. The full project catalog is absent from client JavaScript; the spatial and current-fact read models remain separately versioned and reproducible.

Measured interaction

Repeated local desktop paths painted all points in roughly 0.5 to 0.9 seconds; a real drag sampled 60 fps, 18.5 ms p95 frame time, and no frame over 50 ms. These are local runs, not field percentiles.

Scale path staged safely

A 21-table D1 model, idempotent 196-record import, R2 and PMTiles references, and 100k, 1m, and 5m local metadata tests are committed without switching the production read path or weakening evidence semantics.

Still incomplete: local measurements are not p75 field data or production D1 latency. Current geography remains a large raw payload, initialization still records long tasks above 50 ms, specialist tabs still co-travel with the selected dossier, D1 and R2 are not bound, and vector tiles, cursor pagination, list virtualization, immutable hosting caches, slow-network evidence, and production-like concurrency remain staged work.

Release 30

Seven mine assets across five states make the IBM breadth lane genuinely comparative

The default map now contains 196 source-backed records: 72 Major projects or mine assets and 124 optional Facilities or local schemes. Six additional Indian Bureau of Mines inspection records add bauxite, chromite, manganese, gold, copper, and lead-zinc assets across Chhattisgarh, Jharkhand, Odisha, Rajasthan, and Telangana while preserving the Release 29 Vijay-II iron-ore record.

Seven distinct minerals

Each mine keeps its IBM mine code, registration, mineral, state, district, exact lessee role, dated production or suspension evidence, source pages, document hash, and explicit missing fields.

Lifecycle stays dated

Five production observations, one inspection-dated suspension, and one unresolved post-lease-execution state remain separate. None is silently promoted to current 2026 operating status.

Least misleading position

Official coordinate envelopes, explicitly interpreted UTM-style values, cached named localities, and one named mine-feature representative retain different source and transformation boundaries.

196 points checked

Every active record remains an individual feature. State containment returns 190 matches and the same six explicit NHAI conflicts; district containment covers all points across 165 mapped districts.

Still incomplete: seven records are not a national mine inventory. Current operating state, lease polygons, extraction footprints, post-inspection production, reserves, revenue, tenders, contracts, payments, clearances, closure plans, decommissioning, and audit findings remain unlinked unless a reviewed source supports them.

Release 29

Project types become explorable, and mines become their own evidence entity

The default map now contains 190 source-backed records: 66 Major projects or mine assets and 124 optional Facilities or local schemes. A shareable multi-select taxonomy lets readers isolate 14 reviewed categories, including dams, airports, highways, rail, metro, bridges, ports, energy, water, industrial development, and Mining and Minerals without classifying records from cost or project name alone.

Icons plus precision

One shared pictogram family appears in project-type filters, markers, results, previews, and Project Briefs. Circle, diamond, square, corridor, representative, and unresolved-location treatments still carry the separate spatial meaning.

Markers stay locked

MapLibre now positions a neutral marker anchor while hover, selection, and category visuals animate only inside it. The map no longer destroys and recreates every HTML marker after zoom.

Mine asset, not project

Vijay-II Iron Ore Mine is published as a distinct IBM mine asset with mine code, lessee role, dated FY 2023-24 production, and a stale-status warning. NALCO and NMDC remain mining-development projects.

190 points checked

Every point retains one state and district result across 159 mapped districts. The new mine point is derived from an official IBM Quarry 1 coordinate envelope, not a lease boundary or extraction footprint.

Still incomplete: this is a one-record mine-asset lane, not a national mine inventory. Current mine operating status, lease polygons, post-2024 production, reserves, revenue, clearances, closure status, and audits remain unlinked. Municipal boundaries are not republished because the reviewed official district service prohibits offline export; the map keeps progressive capital, city, town, and village orientation without inventing civic geometry.

Release 28

Major-project coverage reaches 33 state and union-territory scopes

A second reviewed PAIMANA breadth batch adds 25 source-backed Major projects without changing or replacing the first batch. The cumulative lane now contains 50 PAIMANA projects across 33 state or union-territory scopes and 11 official sectors, taking the public directory to 189 records: 65 Major projects and 124 optional Facilities or local schemes.

25 new Major projects

Rail, metro, roads, bridges, ports, pipelines, power, water, industrial corridors, and other large systems broaden the default national first read without using cost alone as the classifier.

50 cumulative PAIMANA records

The reproducible manifest preserves the exact Release 27 selection, adds the reviewed second batch, and reuses cached spatial matches so only new or changed lookups are retrieved.

189 points checked

Every published point returns one state and one district. The refreshed ledger spans 158 mapped districts while the same six earlier NHAI source-state conflicts remain explicit.

Boundaries of this release

  • PAIMANA Original Cost, Anticipated Cost, Cumulative Expenditure, progress, dates, reporting agency, and line ministry remain separately typed. Identical organization names can occupy two exact published roles without being collapsed or inferred as a contractor.
  • All 50 PAIMANA breadth markers remain representative because the Flash Report publishes no project coordinates or geometry. The selected OpenStreetMap entity, query, retrieval date, original coordinate, precision class, transformation, and limitation remain attributable per record.
  • Two NHPC project pages add official locality context for Pakal Dul and Teesta VI. Their other cost, schedule, and status fields are not silently mixed with the PAIMANA snapshot and require a separate semantic review.
  • Delhi Metro Phase V A and the Bhanupalli–Bilaspur–Beri line retain clearly labeled administrative or corridor-end navigation anchors where no source geometry was published. The markers are not presented as project extents or exact worksites.
  • The report's six note-named inconsistent cumulative-expenditure project codes remain excluded, including the two that still appear in the table.
  • Tender, award, signed contract, contractor, payment series, amendment, dispute, audit, package geometry, and final-cost evidence remain explicitly unlinked for the new basic records.
  • Every active record remains an individual precision-aware feature. No lens contains clusters, count bubbles, state-count pills, or zoom-triggered aggregation.
Release 27

Major-project breadth becomes genuinely national

Twenty-five source-backed major projects from MoSPI's May 2026 PAIMANA Flash Report join the default national layer across 16 states or union territories and 10 official infrastructure sectors. The map now opens with 40 Major projects, while all 124 toll-plaza facilities and local urban-service schemes remain preserved, searchable, and available through explicit layers.

25 new Major projects

Airports, rail, metro, industrial corridors, ports, energy, water systems, bridges, roads, and ring-road projects broaden the first read without promoting records by cost alone.

1,987-row source universe

A reproducible extractor preserves every table row and project code, then a reviewed manifest selects the sector-balanced batch without duplicating the earlier PAIMANA sample.

164 points checked

Every published marker returns one state and one district. The refreshed ledger spans 142 mapped districts while the same six earlier NHAI source-state conflicts remain explicit.

Boundaries of this release

  • Original Cost, Anticipated Cost, Cumulative Expenditure, physical progress, and original or revised completion dates keep their exact source meanings. Cumulative Expenditure is not relabeled as contractor payment, actual cost, or final cost.
  • The source-named agency is displayed only as PAIMANA reporting agency. The line ministry or department remains separate, and no contractor, concessionaire, operator, selected bidder, or project company is inferred.
  • PAIMANA publishes no project coordinates or geometry in the reviewed table. Each new marker is a cached, attributable OpenStreetMap facility, locality, or corridor representative and states that limitation directly.
  • A report note says six project codes are omitted for inconsistent cumulative-expenditure data, but two still appear in the table. All six note-named codes are excluded from this batch, and the source contradiction remains documented.
  • Tender, award, signed contract, contractor, payment series, amendment, dispute, audit, package geometry, and final-cost evidence remain explicitly unlinked for these basic records.
  • No lens contains clustering, state-count pills, count bubbles, or automatic aggregation. Every record active in Major, Facilities, or All records remains an individual precision-aware map feature.
Release 26

Major infrastructure leads, without hiding the evidence directory

The default national view now leads with 15 officially scoped central infrastructure projects, while all 124 toll-plaza facilities and local urban-service schemes remain preserved, searchable, and available through explicit Facilities or All records layers. Every active record renders as its own precision-aware mark at every supported zoom.

15 major projects by default

PAIMANA central projects lead the national first read because their reviewed official scope is project or programme level, not because of a cost threshold invented by the interface.

124 optional facilities and schemes

Facilities and All records expose the complete directory, while search spans all 139 published records from any active layer.

Evidence meaning preserved

Exact points, official facilities, localities, corridors, and unresolved locations retain their source-backed coordinates, shapes, labels, and limitations.

Boundaries of this release

  • No project, package, tender, contract, payment, organization, dispute, audit, source, cost, schedule, or spatial record changed.
  • National markers are intentionally small and crisp. Color follows the selected lens, while shape continues to carry spatial precision without relying on color.
  • No lens contains a cluster, count bubble, state pill, or zoom-triggered aggregation. Coverage colors and sorts individual records by reviewed evidence depth.
  • Toll plazas remain facilities unless an official parent-project relationship is linked. AMRUT locality records remain local schemes. The interface does not infer a parent or promote either class to Major.
  • The primary canvas no longer displays an inactive Ask the map control. Search, four primary lenses, progressive lens access, compact filters, result count, and results form the browse first read.
  • The current 139-record dataset has no identical coordinate pairs. Source-backed coordinates are not jittered. Future true collisions require zoom or explicit expansion.
  • Infra retains direct MapLibre, OpenFreeMap Positron, official India geography, evidence-aware markers, and its single right workspace. No React wrapper migration or cross-repository map package is introduced.
Release 25

Urban water and sanitation bring every state into the breadth lane

Thirty-five source-backed AMRUT 2.0 projects now join the public map, one for every state or union territory listed in the Ministry directory. The release takes the directory from 104 to 139 reviewed records while keeping each new project visibly basic until its implementing organization, tender, award, progress, schedule, payment, and deeper evidence are linked.

35 locality-aware records

Nineteen Water Supply and sixteen Sewerage / Septage projects use separately sourced locality representative points, never invented project sites.

35 states and union territories

A deterministic state-balanced selection starts from the official directory's 8,777-project universe and preserves the candidate-to-published review trail.

139 state and district checks

Every unchanged point returns one state and one district. The dataset now spans 123 mapped districts while all six earlier NHAI state conflicts remain explicit.

Boundaries of this release

  • The AMRUT page publishes project title, type, literal Project Cost, milestone, and state and city or ULB scope. It does not publish a durable project id, project coordinate, publication date, implementing authority, contractor, tender, award, signed contract, progress, schedule, payment, amendment, dispute, or audit record.
  • Project Cost remains the exact source label. It is not relabeled as original, sanctioned, tender, award, revised, expenditure, actual, or final cost, and no cost-change conclusion is calculated.
  • A milestone such as Contract Awarded is a source-dated directory label. Without the underlying award record it does not identify the selected organization, award date, contract value, or current construction status.
  • The official pages do not publish project geometry. A one-time, rate-limited, cached OpenStreetMap Nominatim match supplies a locality navigation point with attribution and provenance. Production makes no live geocoder request.
  • The directory footer reports ₹1,97,191.85 crore, while its displayed state rows sum to ₹1,97,191.73 crore. The ₹0.12 crore source-display difference is retained instead of silently reconciled.
  • Karnataka's empty, implausible city row is rejected because it lacks a city identity. Kargil and Bishnupur use reviewed town results rather than same-named district relations.
  • The 35 records are a state-balanced first sample, not a claim that all 8,777 AMRUT projects have been reviewed. The NHAI breadth lane, six deep source ledgers, all prior releases, and every earlier source and spatial record remain intact.
Release 24

Every mapped point gets district context

All 104 published points now have a source-backed mapped-district result. Readers can search and filter by district, see the district in hover or keyboard preview, and inspect the exact containment source and limitation in the Project Brief and Evidence view.

104 points checked

Every exact, official-facility, locality, facility, and representative-corridor point returns one district without changing its stored coordinates or precision.

96 mapped districts

The hashed ledger preserves district and state names, Local Government Directory codes, Census 2011 code when published, dates, source metadata, and per-record hashes.

No district geometry exported

The public service performs the intersection with returnGeometry=false. The app stores attributes only and remains independent of that service at runtime.

Boundaries of this release

  • The filter is labeled Mapped district because it describes the district containing the displayed point, not necessarily the complete district scope of a project, corridor, package, or administrative-area record.
  • Every district state and LGD state code agrees with the separate Release 22 state-containment result for the same unchanged point.
  • A district result does not upgrade an editorial, locality, facility, corridor, or official-facility point to surveyed accuracy. Existing precision shapes and labels remain authoritative.
  • Search, mapped-district filter, selected project, and camera remain shareable in the URL. The district query parameter is view state, not new spatial evidence.
  • The analysis uses the 2026 Esri India service credited to Census of India, Survey of India, Local Government Directory, and Esri India. It is not a directly downloaded Survey of India polygon dataset.
  • The public map remains at 104 records. This release improves geographic discovery and does not claim new project, contract, payment, cost, deadline, dispute, or audit evidence.
Release 23

Six map conflicts get evidence-reviewed outcomes

The six Release 22 state conflicts no longer share one generic warning. Four now have an official-document-supported administrative state for discovery, while Mudipar and Moura remain visibly unresolved because the reviewed evidence cannot support a safe coordinate or state correction.

4 reviewed states

Ghamroj and Jita Kherli Kiranj are discoverable in Haryana; Koyla and Sayed Majra are discoverable in Uttar Pradesh. Their earlier source-state fields remain visible.

2 unresolved locations

Mudipar's published point conflicts with its Chhattisgarh corridor evidence. Moura's Gazette contains conflicting Rupnagar and Himachal Pradesh wording.

6 hashed official sources

Each outcome exposes a direct document, reviewed pages, concise observation, retrieval date, hash, and limitation in the Project Brief and Evidence view.

Boundaries of this release

  • No original RajmargYatra state, coordinate, containment result, CRS, spatial type, or precision class was overwritten.
  • The four reviewed administrative states agree with both a separate official document and the independent containment result. They improve filtering and state-count grouping but do not certify surveyed accuracy.
  • Mudipar and Moura use a dashed outer marker shape, explicit high-attention wording, and a dedicated unresolved-location filter. They remain discoverable from both state signals.
  • No authoritative replacement coordinate was located for Mudipar. The map does not substitute a locality, district centroid, corridor midpoint, or invented decimal point.
  • Moura remains unresolved because the official Gazette itself combines Rupnagar district with Himachal Pradesh wording. The product does not choose a winner without a correction or newer authoritative record.
  • A reviewed state difference or unresolved location is an evidence condition, not an allegation, audit finding, or conclusion about project quality, compliance, waste, misconduct, or corruption.
  • The public map remains at 104 records. This release deepens spatial truth; it does not claim a new coverage count or add contract, payment, cost, deadline, dispute, or audit evidence.
Release 22

Every marker gets an independent state check

All 104 unchanged marker coordinates now pass through a separate 2026 administrative point-in-polygon analysis. Ninety-eight agree with the project's declared source scope; six NHAI breadth records return a different state, and those conflicts are now prominent in hover, Project Brief, attention-filtered discovery, and the full Evidence view instead of being hidden by the source label.

104 points checked

Every exact, official-facility, locality, facility, and representative-corridor point resolves to one state polygon without changing its stored coordinates or precision class.

98 matches · 6 conflicts

The hashed ledger preserves source scope, returned state, LGD and Census codes, WGS 84 input, query date, method, and per-record result.

No silent correction

Mudipar, Ghamroj, Jita Kherli Kiranj, Moura, Koyla, and Sayed Majra keep both the NHAI state label and the differing containment result visible.

Boundaries of this release

  • The analysis uses the 2026 India Admin Boundaries state layer, credited to Census of India, Survey of India, Local Government Directory, and Esri India. It is a secondary dissemination service, not a directly downloaded Survey of India polygon file.
  • The service receives each original EPSG:4326 point and returns only matching state attributes. No polygon geometry is downloaded, stored, simplified, republished, or bundled, respecting the source's no-offline-export boundary.
  • A containment match checks the mapped point, not the full extent of a corridor or multi-state project, and it never upgrades an official facility or editorial point to surveyed accuracy.
  • The six conflicts are source-review flags, not allegations, corrections, or proof that a project is misplaced. The original point, source state, independent result, and evidence limitation remain available together.
  • The six conflicts are Mudipar: Chhattisgarh versus Rajasthan; Ghamroj and Jita Kherli Kiranj: Delhi versus Haryana; Moura: Himachal Pradesh versus Punjab; and Koyla and Sayed Majra: Uttarakhand versus Uttar Pradesh.
  • No project, contract, payment, dispute, cost, deadline, or organization record was removed or relabeled. Release 21's 104-record directory and all earlier evidence remain intact.
Release 21

The national map becomes a shareable evidence directory

All 104 records can now be narrowed by evidence depth, freshness flags, spatial precision, named organization coverage, and attention severity without weakening the underlying truth contract. Search, lens, filters, selected project, and map camera are written into the URL, so a reader can copy the exact investigation view from either browse or Project Brief.

One URL, one map view

Search, lens, eight deterministic filters, selected record, longitude, latitude, and zoom survive a shared link and browser history navigation.

Evidence depth is discoverable

Basic, spatial, timeline, contract, payment, and deep-dossier tiers describe what has been linked, never whether a project is good or bad.

Freshness and roles stay literal

Readers can isolate explicit newer-source warnings or missing named delivery roles without turning either absence into a factual conclusion.

Boundaries of this release

  • The freshness filter surfaces deterministic review signals already supported by dated evidence. “No freshness flag” is not a guarantee that every source is current.
  • Named source role means only that the reviewed record publishes a role and organization. It does not relabel a collection agency, concessionaire, operator, selected bidder, project company, or combined source role.
  • Spatial filtering distinguishes exact points, official facility points, representative places, representative corridors, and conflicting official records. It does not upgrade any record’s precision.
  • Camera coordinates in the URL describe the reader’s viewport, not project evidence. Project coordinates and their original provenance remain unchanged.
  • At Release 21, administrative containment still relied on source state, highway, chainage, corridor, office context, and reviewed India bounds. Release 22 later adds the independent polygon check without rewriting this historical limitation.
  • This release adds discovery behavior, not new project records or deeper contracts. Release 20’s 104 records and all prior evidence ledgers remain intact.
Release 20

The map passes its first national coverage milestone

Eighty current NHAI toll-plaza records now enter through a reproducible breadth pipeline, taking the public map from 24 to 104 source-backed records. The batch spans 23 states and union territories while every new record remains visibly basic until construction, contract, payment, dispute, or audit evidence is linked.

104 mapped records

National zoom uses restrained state counts, then reveals precision-aware project markers as the reader moves closer.

1,217 candidates, 80 published

The committed pipeline preserves candidate, retrieval, normalization, deduplication, entity, spatial, review, and publication stages.

23 states and union territories

A deterministic four-per-state cap prevents the first batch from becoming a few-state sample and keeps the selection reproducible.

Boundaries of this release

  • New records publish only stable NHAI identity, active source-record state, supported corridor and office scope, official facility coordinates, highway and chainage, rate dates, user fee, and exact Collection Agency Name when present.
  • Official facility coordinates are not presented as surveyed exact sites. The validator checks coordinate order, India bounds, the source-provided state, highway, chainage, and PIU or regional-office context.
  • Active means only that the source record returned active when reviewed. It is not a construction, compliance, performance, traffic, revenue, or contract-quality judgment.
  • A car user fee is not project cost, revenue, payment, award value, or final cost. Thirteen records with passed rate-revision dates stay explicitly stale rather than being silently treated as current.
  • Collection Agency Name is preserved as that exact role. It is not relabeled as contractor, concessionaire, operator, selected bidder, or project company.
  • Contact names, phone numbers, email addresses, nearby-service contacts, and embedded source documents are discarded before the reviewed snapshot is written.
  • All 24 earlier records, six deep source ledgers, Project Brief behavior, map interaction, geography, and specialist evidence tabs remain intact.
Release 19

Every project now opens with a complete first read

The selected-project Overview is now a calm, continuous Project Brief. It answers what the project is, where the marker comes from, what the latest reviewed record reports, how compatible costs or dates changed, who holds each sourced role, what contract evidence exists, why attention appears, and what remains unknown before asking a reader to open specialist tabs.

Understand the project in seconds

A plain-language summary and four-row current read put reported state, money, schedule, and mapped precision first without hiding the map.

Evidence depth is explicit

Every record receives a deterministic coverage tier from Basic official record through Deep evidence dossier. The tier describes linked evidence, not project quality.

Highlights explain themselves

Cost, schedule, procurement, freshness, and attention statements expose their source context, date, limitation, and direct path into deeper evidence.

Boundaries of this release

  • AI assisted the wording at build time, but structured official fields, deterministic comparisons, and linked sources remain the factual authority. No live AI request is added to hover or project opening.
  • “No upward revision reported” describes the reviewed fields only. It is not a health, value, efficiency, or compliance judgment, and a revised value is never relabeled as actual or final cost.
  • Organization names keep their exact sourced roles. Selected bidder, concessionaire, project company, operator, fee agency, payee, authority, and combined source roles are not silently converted into “contractor.”
  • Attention signals explain the observed value or date and remain review prompts. The brief makes no supported conclusion about cause, blame, waste, misconduct, or corruption.
  • Overview summarizes and links into Timeline, Money, Organizations, Packages, Contracts, and Evidence rather than duplicating each full dossier.
  • All 24 records, Release 18 map behavior, and Releases 1 through 17 evidence remain intact. National coverage is still an incomplete sample.
Release 18

India becomes an explorable map

The map now combines natural full-screen gestures, official state and union-territory orientation, a progressive city hierarchy, useful project previews, and spatial-precision-aware selection. It feels immediately explorable while every project placement and every geographic layer keeps its own evidence boundary.

Official geographic context

493 Survey of India state and union-territory line strings, 36 label anchors, and progressive Indian place labels restore orientation without letting surrounding geography compete.

Reproducible derivation

The release records source URLs, PDF hashes, the embedded Lambert Conformal Conic CRS, control points, WGS 84 transformation, simplification, and output counts.

Interaction respects precision

Exact points, facilities, localities, and representative corridors open at deliberately different scales. The preview explains precision, current evidence, and why an attention signal appears.

Boundaries of this release

  • The 1:16M state geometry is generalized orientation context, not cadastral, surveyed local, district, package, corridor, facility, or project-site geometry.
  • City, town, and village labels use OpenMapTiles place points clipped to the official India outline. They are orientation labels, not evidence for a project position.
  • Direct wheel, trackpad, drag, and pinch gestures are enabled on the full-screen map. Pitch and rotation remain constrained, and Reset to India remains available.
  • A representative corridor still opens around its supported point because reviewed corridor geometry is not yet available. The camera does not imply a line or invented extent.
  • Closing detail restores the prior browse camera unless the user deliberately changed the camera while detail was open. Hover and keyboard preview never move it.
  • All 24 records and Release 17 evidence remain intact. National coverage is still an incomplete sample; Release 19 improves how each record is understood before breadth-lane expansion.
Release 17

From solicitation to executed contract

Raha's 2022 fee-agency RFP now connects to a later NHAI executed-contract register row for the same plaza and procurement scope. The release adds the source-dated company, accepted Annual Remittance, contract period, and plaza code while preserving every missing document and current-status boundary.

24 records, 7 exact toll points

The map and exact km 254.514 Raha position remain unchanged. The evidence trail deepens without inventing a new marker or moving the official point.

One RFP-to-contract join

Raha, Nagaon district, km 205.000-273.489 scope, ₹51.80 crore APC, contract chronology, and official office context support the join.

Accepted remittance, narrowly defined

₹51.90 crore Annual Remittance is ₹0.10 crore or 0.19% above APC. It is not actual collection, revenue, profit, overrun, or performance.

Boundaries of this release

  • The register names M B Consortium only as the company for a regular executed fee-agency contract from 9 December 2022 to 9 December 2023. The ended period does not establish the current agency or operator.
  • The 2022 RFP still does not publish its bid-opening result, letter of award, or signed contract. The later register partially resolves the outcome without replacing those absent records.
  • The ₹51.80 crore APC and ₹51.90 crore accepted Annual Remittance are compatible procurement fields. ₹1,245.88 crore project capital cost and ₹212.84 crore historic project-stretch revenue remain separate.
  • M B Consortium in the executed register and M/s M.B. Consortium in NHTIS retain their exact strings and source roles. No construction role, transfer, legal-entity normalization, or current status is inferred.
  • The register's PIU cell visibly reads “37 Nagaon,” while older and later official sources use PIU Nagaon and PIU Guwahati. The source difference remains visible.
  • Actual collection, remittance receipts, amendments, performance, current rate and revenue, construction award and payments, revised or final cost, and audit findings remain unlinked.
Release 16

An executed contract, not an inferred award

Pahammawlein adds Meghalaya's first reviewed fee-plaza trail and the product's first official executed fee-agency contract entry. The exact map point, NHTIS operating record, and NHAI contract register join through the same plaza name, km 13.550 chainage, NH-40 corridor, PIU, and regional office.

24 records, 7 exact toll points

The Meghalaya plaza uses the published 25.99328, 91.860491 WGS 84 point, with chainage, lane count, source page, document hash, and corridor validation preserved.

Six reviewed ledgers

The new ledger validates plaza code 379006, the source-dated company role, contract type and period, APC, accepted Annual Remittance, and missing current-status fields.

One compatible comparison

₹42.81 crore accepted Annual Remittance is ₹0.23 crore or 0.54% above the ₹42.58 crore APC estimate. It is not actual toll collection or performance.

Boundaries of this release

  • The register names M/s Skylark Infra Engineering Pvt. Ltd. only as the company for the executed regular fee-agency contract from 18 November 2022 to 18 November 2023. It is not relabeled as construction contractor or current operator.
  • NHTIS separately names MB Consortium in its combined Concessionaire / OMT Contractor field. No transfer, corporate relationship, succession, or present-day role is inferred between the organizations.
  • The ₹42.58 crore APC and ₹42.81 crore Annual Remittance are comparable procurement fields from one register row. ₹536 crore project capital cost and ₹24.41 crore historic project-stretch revenue remain separate.
  • The contract period ended on 18 November 2023 and the NHTIS fee schedule was due for revision on 31 March 2026. Current agency, rate, revenue, remittance receipts, and performance require newer evidence.
  • Jorbat-Shillong in the contract register and Jorabat-Shillong in the other NHAI records remain a visible source spelling difference.
  • Signed contract text, tender and award file, payments, amendments, construction award and expenditure, revised or final cost, and audit findings remain unlinked.
Release 15

Northeast evidence, without false equivalence

Raha (Saragaon) adds the first reviewed Assam fee-plaza trail: an exact NHAI point, the official NHTIS operating record, and a 2022 fee-agency RFP joined by the same plaza name and km 254.514 chainage. The public brief keeps procurement estimate, bidder remittance, project capital cost, historic toll revenue, and a stale fee schedule separate.

23 records, 6 exact toll points

Raha adds a Northeast record at 26.245678, 92.541521 in Nagaon district, with WGS 84, source page, document hash, chainage, and validation preserved.

Five reviewed ledgers

The new machine-readable ledger validates the exact point, ₹51.80 crore APC, dated NHTIS money, bid schedule, source differences, and missing award fields.

Four money meanings stay apart

₹51.80 crore APC, an unpublished Annual Remittance, ₹1,245.88 crore project capital cost, and ₹212.84 crore historic project-stretch revenue are not compared or combined.

Boundaries of this release

  • NHTIS reports commercial operation from 22 February 2017 and names M/s M.B. Consortium only in its combined Concessionaire / OMT Contractor role. It is not silently relabeled as the construction contractor or selected 2022 fee agency.
  • The RFP publishes a one-year opportunity, 4 August bid deadline, 5 August scheduled opening, and a planned LOA window. It does not publish the opening result, award, selected agency, signed contract, accepted Annual Remittance, or actual collection.
  • The ₹212.84 crore figure is cumulative toll revenue for the entire project stretch through 30 October 2024. It is not annual or current revenue, capital cost, an award, expenditure, or final cost.
  • The accessible fee schedule was due for revision on 31 March 2026. Its ₹120 car fee is displayed as dated evidence, not claimed as the current 2026-27 rate.
  • Nagao-Daboka-Udauli versus near-Nagaon to Guwahati corridor wording, NH-37 versus NH-27 numbering, and PIU Nagaon versus PIU Guwahati remain visible source differences.
  • Underlying construction-package awards and payments, revised or final cost, current rate and revenue, amendments, and audit findings remain unlinked.
Release 14

Four roles, one concession trail

Sadahalli now links its exact km 538 plaza and km 534.720-556.840 package to the original NHAI RFP and signed concession agreement. Selected bidder, project company, completed-projects organization, and current NHTIS organization remain four source-scoped identities rather than one guessed contractor history.

Exact package and plaza join

The RFP, agreement, completed-projects row, and NHTIS record share the same 22.12 km NH-7 or NH-44 corridor, with Sadahalli at km 538.

Signed concession terms

The agreement records a ₹61.20 crore authority grant, ₹34 crore performance security, 20-year concession, and 730-day scheduled upgradation period.

Organization roles stay separate

The reviewed sources name Navayuga Engineering, Navayuga Devanahalli Tollway, Navyuga Road Projects, and Athaang Devanahalli under different roles and dates.

Boundaries of this release

  • The ₹680 crore RFP estimate, agreement Total Project Cost ceiling input, and NHTIS capital cost share a number but not a definition. None is labeled actual or final cost.
  • The ₹61.20 crore authority grant, ₹34 crore performance security, ₹13.60 crore bid security, ₹458.60 crore historic toll revenue, and ₹120 car fee remain separate money types.
  • The agreement says Navayuga Engineering promoted the original project company. No reviewed source establishes the relationship to Navyuga Road Projects or the later Athaang NHTIS organization.
  • The 30 April 2010 agreement is 81 days after the 8 February LOA, 36 days beyond the stated signing window. No extension or waiver is linked, so this is an evidence gap, not a delay or breach finding.
  • The RFP's Bijapur-Hungund footer mismatch remains visible, while the project-specific title, package number, chainage, and signed agreement control the Sadahalli join.
  • Grant disbursement, construction payments, amendments, final cost, current toll revenue, organization-transfer evidence, and audit findings remain unlinked.
Release 13

One package, two plazas

Sardewadi joins Patas as a second mapped fee plaza on Pune–Solapur Package I. The product now carries one shared project-money record, one shared package award, a compatible pre-bid cost revision, and two explicitly conflicting official coordinate records without double counting or false precision.

22 records, four spatial shapes

The map now has 5 exact toll points, 2 official facility points, and 15 representative records. Patas and Sardewadi use a diamond because the later official coordinate list is indicative.

One ₹378.70 crore record

Both NHTIS pages repeat cumulative toll revenue for the entire project stretch through 31 December 2016. The interface counts it once, never ₹378.70 crore per plaza.

Compatible cost change only

NHAI's pre-bid Addendum No. 2 changes RFP Total Project Cost from ₹922 crore to ₹1,110 crore, +₹188 crore or +20.39%.

Boundaries of this release

  • The ₹1,371 crore NHTIS project capital cost and ₹378.70 crore project-stretch toll revenue are shared fields repeated on two plaza pages. Neither is doubled.
  • The ₹922 crore to ₹1,110 crore change is a compatible bid-document revision before bid submission, not a later construction overrun, actual cost, expenditure, or final cost.
  • The later ₹1,371 crore capital-cost field has a different source definition and is not appended to the bid-document series.
  • Patas's two official coordinates are 4.92 km apart and Sardewadi's are 224.75 km apart. The later corridor-aligned IHMCL points are mapped as indicative facility points, while both conflicts remain visible.
  • The ₹299 crore authority grant, 21-year concession, 910-day construction period, and ₹55.5 crore performance security belong to one shared package award, not separate plaza awards.
  • Current toll revenue, plaza-level collection, final project cost, construction payments, amendments, audit findings, and the reason for the coordinate conflicts remain unlinked.
Release 12

Four payments are not one contract

Tundla now connects four exact NHAI cheque rows from 2011 and 2012 to a separately bounded 2013 fee-agency RFP, without implying that the payee won the later procurement or that the reviewed rows form a complete contract.

Precision survives the join

The exact official point at km 224.950 stays distinct from the RFP's rounded km 225.000 plaza and narrower km 219.000 to 250.500 solicitation limits.

Four reviewed cheque rows

Two official expenditure registers name four payments to Cannon totalling ₹33,63,639 across only those displayed entries.

Opposite money directions

Authority-to-payee cheque rows remain separate from the later ₹47.75 crore APC estimate and the blank bidder-to-authority Annual Remittance field.

Boundaries of this release

  • ₹33,63,639 is only the sum of four reviewed rows, not a contract value, complete payment series, monthly amount, project cost, toll revenue, or final cost.
  • The source spelling “M/s Cannon Mangement Security Services” remains exact; no silent organization-name correction or entity resolution is claimed.
  • The repeated ₹14,58,887 amount under two different cheque references is not interpreted as either a contractual pattern or a duplicate error.
  • The 2013 RFP does not identify a selected agency, award, filled Annual Remittance, actual collection, or relationship to the earlier payee.
  • AE Tollway Limited remains in the current combined NHTIS role; the evidence does not connect it to Cannon or to the RFP outcome.
Release 11

One plaza, three procurement baselines

Barsoni now connects three official NHAI fee-agency RFPs from 2014, 2019, and 2024 to one separately typed performance-security refund, while keeping every missing award result and actual collection figure visible.

2014 to 2024 trail

The same km 416.000 plaza and km 410.700 to 447.000 Purnea–Dalkhola section anchor all three RFPs to the exact mapped record.

Published APC series

NHAI published Annual Potential Collection of ₹17.98 crore, ₹35.18 crore, and ₹41.79 crore for the three one-year solicitations.

Machine-readable source ledger

Reviewed facts now carry entity keys, page references, document hashes, typed money, source differences, and outcome boundaries outside presentation code.

Boundaries of this release

  • Annual Potential Collection is NHAI's procurement estimate, not actual toll revenue, a bidder offer, award amount, authority receipt, project cost, or final cost.
  • The ₹55,41,415 July 2014 entry is one cash performance-security refund to Sahakar Global, not construction expenditure, toll collection, or total payment.
  • None of the three linked RFPs publishes its selected agency, bid-opening result, letter of award, signed contract, bidder payment, or actual collection series.
  • The 2024 scope adds adjacent toilet-block upkeep, so the APC sequence is contextual procurement evidence rather than a pure like-for-like performance measure.
  • One 2014 schedule page says West Bengal while the project-specific RFP sections, NHTIS, and official point agree on Bihar. The discrepancy remains visible.
Release 10

The post-concession gap gets a tender trail

Laling now links IRCON's reported 21 April 2026 concession end to NHAI's 6 July 2026 solicitation for a user-fee agency covering the named Laling and Chandwad plazas.

Post-concession sequence

The public brief and timeline now show the concession date, tender publication, bid deadline, and scheduled opening without inventing a transition date.

Exact tender identity

Tender 2026_NHAI_283102_1 and its reference, authority, bundled scope, 6 July publication, 13 July closing, and 14 July scheduled opening are linked.

Solicitation, not award

The interface says selected agency, award, tender value, payment, and current operator are not published in the linked listing.

Boundaries of this release

  • The tender covers Laling and Chandwad together. Its scope and any future result are not attributed to Laling alone.
  • Publishing a user-fee agency tender does not establish an award, who collected fees after 21 April, or who operates the corridor now.
  • A user-fee agency is not relabeled as the construction contractor, concessionaire, project company, or corridor operator.
  • Missing tender value, EMD, award amount, selected agency, and award date remain “not published,” never zero.
  • The official active-tender list is dynamic. The exact tender ID is preserved for portal lookup while a stable direct detail or award-result link remains missing.
Release 9

The historic claim gets a dated outcome

Laling's Pimpalgaon–Dhule trail now moves from NHAI's 2018 arbitration disclosure to two final Delhi High Court orders dated 16 April 2024, plus a separate IRCON operating-company record dated 31 March 2025.

2018 → 2024 legal trail

Both NHAI and Ircon Soma court petitions were withdrawn after the parties reported settlement under Vivad Se Vishwas-II.

Dated operating record

IRCON reports the linked 118.158 km project complete in 2010–11, toll collection since April 2010, and a 25-day concession extension to 21 April 2026.

Unknown money stays unknown

The original ₹942.52 crore demand remains a claim. Award, settlement, and payment amounts are not published in the linked orders.

Boundaries of this release

  • Withdrawal after settlement is not presented as a win, loss, admission, liability finding, acceptance of the original demand, or evidence of misconduct.
  • The Court's direction returning NHAI's deposit plus interest to NHAI is a court-deposit disposition, not a published settlement amount, payment, or project recovery.
  • IRCON's operating status is dated 31 March 2025. Its reported 21 April 2026 concession end has passed, so current operation now requires a newer source.
  • NHTIS, IRCON, and NHAI publish different concession dates, chainage limits, or rounded lengths. All remain visible instead of being silently reconciled.
  • The settlement instrument, award and settlement amounts, full payment series, final project cost, amendments, and audit findings remain unlinked.
Release 8

India returns to the center

The map now owns the majority of the screen. One adaptive workspace on the right alternates between discovery and a plain-language project brief, while the full official India outline, selected marker, filters, lens, results, and camera remain connected.

One map workspace

Browse and detail no longer occupy opposite sides. Returning to results preserves the active query, filters, lens, ordering, scroll position, selected record, and map camera.

21 spatial records

Every marker now carries original coordinates, WGS 84 reference, spatial type, source, retrieval date, transformation, validation, and conflict state.

Public project brief

Overview begins with a sourced TL;DR, then separates current state, compatible cost and deadline movement, timeline, organization roles, evidence, missing links, and location precision.

Boundaries of this release

  • Only the 6 toll plazas use exact published coordinates. The other 15 markers are visibly encoded and described as representative facility, locality, or corridor points.
  • A representative point is not project geometry, a package extent, a surveyed site, or proof that all work occurs at that point.
  • “No upward revision reported” compares compatible fields in one source record. It is not a final-cost claim or a green verdict about project health.
  • Organization labels preserve the role printed by the source. A concessionaire, operator, selected bidder, authority, and combined source role are not silently converted into contractor.
Release 7

A second contract history, with allegations kept honest

Laling now connects the Pimpalgaon–Dhule package to a 2012 positive-grant payment and NHAI's 2018 disclosure of a ₹942.52 crore arbitration claim, without presenting either as project cost or carrying an old dispute status forward as current.

2005–2018 trail

The dossier now links the concession agreement, package start, commercial operation, grant payment, and dated arbitration disclosure in one chronological view.

₹6,85,16,728 payment

NHAI's February 2012 register names Ircon Soma Tollway, PIU Nashik, the cheque reference, purpose, amount, and e-payment indicator.

Claim, not finding

The claimant's five disclosed claim bases are shown as allegations. The claim amount is not an award, accepted liability, payment, cost overrun, or evidence of misconduct.

Boundaries of this release

  • NHAI described the arbitration as pending on 16 November 2018. No later outcome is linked, so the product does not call it currently pending.
  • One positive-grant payment is not the total grant, total disbursed, accepted contract value, project cost, or final cost.
  • The ₹942.52 crore figure is the claimant's disclosed demand, not a tribunal award, payment, accepted liability, or verified loss.
  • The full grant and payment series, amendments, original award, final cost, audit findings, and current dispute outcome remain unlinked.
Release 6

From one payment to live balance works

Pottipadu now links its road package to an official 2019 payment entry and the government portal's current ₹21.59 crore balance-works tender, while keeping payment, tender value, project cost, and user fee separate.

Contract timeline

The dossier now moves chronologically from toll operation and package start through an interim payment, published fee dates, and the 2026 balance-works tender.

₹3,34,65,371 payment

NHAI's July 2019 expenditure register names the payee, cheque reference, IPC purpose, amount, and e-payment status.

Live tender status

The government portal still showed technical bid opening in progress on 14 July after a scheduled 22 May opening date, so the product raises a review signal rather than a delay finding.

Boundaries of this release

  • A 2018 NHAI planning-status report prints Package II's exact km 1050.680–1076.480 limits, upgrading Pottipadu from medium to high join confidence.
  • One IPC payment is not total expenditure, accepted contract value, final cost, or proof of completion.
  • The ₹21.59 crore balance-works tender value is not an award amount, payment, cost overrun, or final project cost.
  • “Under Risk and Cost of the EPC Contractor” is the official tender title. It is not converted into a finding about liability, cause, recovery, or misconduct.
  • The earlier award, complete payment series, amendments, recovery outcome, and audit evidence remain unlinked.
Release 5

Every toll gets a package trail

All six toll-plaza records now reach an official highway-package candidate, with five exact-chainage joins and one clearly labeled medium-confidence corridor join.

6 of 6 package trails

Barsoni, Laling, Pottipadu, and Tundla join Sadahalli and Patas with package scope, delivery model, lanes, start date, and source-named organization.

Confidence stays visible

Five joins align on exact chainage. Pottipadu remains medium confidence because its package row omits the package endpoints and is supported by named and adjacent corridor evidence.

Official differences survive

Length, end-chainage, highway renumbering, project granularity, and operating-versus-package organization differences stay explicit.

Boundaries of this release

  • A package trail is a record-linkage claim, not proof of a complete contract, payment, or ownership history.
  • Pottipadu is not upgraded to high confidence without a source printing the package's own exact endpoints.
  • NHAI's combined contractor or concessionaire register field remains exactly that; it is not silently relabeled as awarded contractor.
  • Original award evidence is still available only for Patas. Awards, amendments, payments, final costs, and audit findings for the other packages remain unlinked.
Release 4

The first award trail

Patas now reaches the original NHAI letter of award and acceptance, connecting the physical toll plaza to the selected bidder and the financial and delivery terms that NHAI actually accepted.

Bid-to-road timeline

Bid submission, letter of award, LOA acceptance, concession agreement, package start, and commercial operation appear in one evidence-backed sequence.

Selected bidder

The Navinya Buildcon–Atlantia consortium is distinct from the later Pune Solapur Expressways project SPV and toll record.

Money stays typed

The accepted ₹299 crore authority grant sits apart from project capital cost, total project cost, user fee, awarded construction value, and expenditure.

Boundaries of this release

  • The award evidence comes from the original NHAI concession volume containing the signed LOA and bidder acceptance.
  • The ₹299 crore figure is a grant quoted by the selected bidder and payable by NHAI under the RFP. It is not labeled contract value.
  • A 22 versus 24 December 2008 bid-date discrepancy inside the official volume remains visible.
  • Bid evaluation, construction subcontracts, grant disbursement, amendments, payments, final cost, and audit findings remain unlinked.
Release 3

Packages beneath the dots

Sadahalli and Patas now connect their fee-plaza records to official highway-package evidence, with organization roles and source differences kept visible.

High-confidence joins

2 of 6 toll plazas now expose the underlying package, linked by name, highway, chainage, and plaza position.

Role-safe organizations

NHTIS toll-record organization, combined contractor or concessionaire register field, and named concessionaire remain distinct source roles.

Conflicts stay visible

Patas shows both official chainage and cost variants without converting unlike source fields into a cost-overrun claim.

Boundaries of this release

  • A package join is labeled high confidence only when the official chainage, highway, package name, and plaza position align.
  • NHAI's completed-projects register combines contractor and concessionaire in one column, so the product preserves that combined label.
  • The Pune–Solapur Independent Engineer RFP cites a concession agreement; it is not presented as the original award record.
  • Original award recommendations, works subcontracts, amendments, payments, and audit findings are still not joined.
Release 2

Toll dots become highway records

Every toll-plaza marker now resolves to an officially published coordinate and carries the highway context and named operator available in NHAI records.

Exact toll placement

All 6 toll markers now use NHAI latitude and longitude, with chainage, project stretch, and plaza lane count.

Operating context

Concessionaire or OMT contractor, project model, PIU, regional office, tollable length, and concession period where published.

Fee freshness

Published car fee and effective date are paired with a visible warning when the revision-due date has passed.

Boundaries of this release

  • Coordinate evidence comes from an official 2017 NHAI plaza annexure and is linked separately from the NHTIS operating record.
  • “Concessionaire / OMT contractor” is the combined source category; the product does not silently convert it into an awarded works contractor.
  • Fee schedules may be stale when the source page’s revision-due date has passed.
  • Contract documents, award value, amendments, and payments are still not joined.
Release 1

The evidence-first map

A working full-viewport India map with the first source-backed national project layer and the system for inspecting evidence without leaving geography behind.

Map experience

Seven working lenses, search, filters, hover and keyboard previews, project selection, mobile sheets, and map-failure fallback.

First data slice

15 PAIMANA central projects and 6 NHTIS toll plazas. Every location is labeled by precision.

Evidence dossiers

Progress, costs, dates, organizations, attention signals, source links, and explicit missing fields.

Boundaries of this release

  • Project markers are an editorial sample, not complete nationwide coverage.
  • Most toll and corridor coordinates are approximate locality or corridor placements.
  • Tender packages, contracts, amendments, expenditure, and audit findings are not linked yet.
  • Attention signals are arithmetic prompts, not allegations of corruption.
Next

Continue the scale foundation and nationwide evidence expansion

Keep the accepted visual and progressive-delivery system stable while splitting specialist evidence payloads, preparing production-grade indexed reads and immutable geography, adding authoritative breadth records, and deepening a smaller stream of contract, payment, dispute, and audit dossiers.